Installing the Hardware
1.
Unpack the two 6AWG red and two black DC jumper cables.
2.
Flip open the touch-safe lug landing cover on the left-side terminal block.
3.
Attach the short pair of red and black DC jumper cables to the left-side
terminals—red cable to the top terminal (+) and black cable to the bottom
one (-).
4.
Secure each connection with a pair of 1/4-20 lug nuts; tighten to a maximum
torque of 62.0 inch-lbs (7 Newton-meters).
5.
Snap the cover shut.
6.
Attach the remaining ends to the bottom (BATTERY B) terminal block of
the chassis—red cable to the top terminal (RETURN) and black to bottom
one (-48V).
7.
Secure the connections with pairs of lock washers and lug nuts; tighten to a
maximum torque of 62.0 inch-lbs (7 Newton-meters).
8.
Use the provided metal loops on the chassis to dress the cables with tie
wraps.
Note:
Dress the DC jumper cables so the push-through air filter and fan
tray can be serviced from the rear of the chassis.
9.
Repeat this procedure for the right-side self connections using the long
pair of DC jumper cables.
10. Install the safety cover.
11. Connect the control cable from J1 (right-side flat connector) on the shelf to
the chassis connector labeled AC STATUS/CTL.
12. Insert the AC power cords for each power module into connectors 2 and 3
on the shelf.
31
27/153 30-CRA 119 1170/1 Uen A
|
2010-04-09
Summary of Contents for SmartEdge 600
Page 1: ...SmartEdge 600 Router Hardware Guide Release 6 3 INSTALLATION 27 153 30 CRA 119 1170 1 Uen A ...
Page 6: ...SmartEdge 600 Router Hardware Guide 27 153 30 CRA 119 1170 1 Uen A 2010 04 09 ...
Page 26: ...SmartEdge 600 Router Hardware Guide 20 27 153 30 CRA 119 1170 1 Uen A 2010 04 09 ...
Page 108: ...SmartEdge 600 Router Hardware Guide 102 27 153 30 CRA 119 1170 1 Uen A 2010 04 09 ...
Page 112: ...SmartEdge 600 Router Hardware Guide 106 27 153 30 CRA 119 1170 1 Uen A 2010 04 09 ...