16)  Install  motor 

(15)

  with  gasket 

(14D)

,  using  hex  head  cap 

screws 

(12c)

 and torque bolts to 55 ft-lbs.

The auger Drive iS noW reaDY for uSe.

*

nal end of output shaft. Press bearing on slowly until it is just 

seated against bearing cup 

(11D)

. With a slight press load still 

applied, rotate base 

(1)

 by hand to ensure roller bearings are 

rotating evenly and smoothly. Inner bearing cone 

(11c)

 may 

require additional press load to reach proper bearing preload.  

If roller bearings are seated properly, continue on to set and 

check bearing preload.

ShafT bearing PreloaD: Proper shaft bearing preload is 

achieved when torque required to rotate base is 50 to 80 in-

lbs. This rolling torque is equal to a force of approximately 11 

to 18 lbs if pulling on base flange to rotate base (1). This may 

be determined by feel or by using a fish scale or similar mea-

suring device to check rolling torque. 

8) 

Install shims 

(14a)

 over internal end of output shaft 

(2)

. Shims 

should slide all the way down to outer bearing cone 

(11c)

where  they  will  rest. The  same  number  (quantity)  of  shims 

removed  from  unit  during  disassembly  should  be  returned.  

Follow shims with split ring segments 

(14c)

. Segments will 

sit directly on top of bearing shims.

noTe:  Quantity  of  shims  (14a)  may  vary  from  unit  to  unit.  

bearing  preload,  set  at  the  factory,  determines  quantity  of 

shims.

9) 

Install the locking ring 

(14b) 

onto output shaft.

10)  Lightly  grease  a  new  o-ring 

(10a)

  and  install  it  into  o-ring 

groove in base 

(1)

. Assemble ring gear 

(8)

 to base 

(1)

. Re-

fer back to scribe marks made across external joints of gear 

drive prior to Disassembly Procedure. Line up scribe marks  

between ring gear and base to give

 

correct hole alignment.

noTe:  be  certain  that  o-ring  (10a)  stays  seated  in  groove 

during Step 10.

11)  Install secondary carrier assembly into unit. Carrier assembly 

should  be  installed  with  hub  side  down 

(24  tooth  spline)

.  

Rotate carrier assembly back and forth to mesh secondary 

planet  gear  teeth 

(7)

  with  ring  gear 

(8)

  teeth.  Once  teeth 

mesh, let secondary carrier slide down until it contacts with 

output shaft spline. The carrier splined hub

 

should spline onto 

output shaft. Carrier hub will rest on top of locking ring 

(14b)

 

when splines are fully engaged. 

12)  Install the carrier cup washer 

(9b)

.

Single  stage:  Install  input  gear 

(4)

,  input  thrust  washer 

(9a)

.

Double Stage: Install secondary sun gear 

(6)

 primary car-

rier  assembly

  (5) 

input  gear 

(4)

,  and  input 

thrust washer 

(9a)

.

13)   Grease a new o-ring 

(10a)

 and install it into bottom of cover/ 

bail assembly

 (3)

. Refer back to scribe marks made across 

external joints prior to Disassembly Procedure. Line up scribe 

marks between cover/bail assembly and ring gear 

(8) 

so that 

orientation of motor mount holes and oil plug are back to their 

original positions.

noTe:  be  certain  o-ring  (10a)  stays  seated  in  cover/bail  

assembly during Step 13. 

14)  Install all twelve of the 7/16 lockwashers 

(12b)

 and the 7/16 

hex capscrews 

(12a)

 and torque to 70 ft-lbs.

15)  Fill unit with oil per the capacity and lubricant recommenda-

tions posted on page 4.

Summary of Contents for 50 Series

Page 1: ... version SMD50L Ac NOTE Individual customer specifications spindle mounting sprocket pilot brake assembly etc may vary from exploded drawing and standard part num bers shown If applicable refer to customer drawing for details 54 Motor Number 50 Model 2 Shaft 1 Bail Boss f Motor Supplier Example Part Number 05 Ratio ...

Page 2: ...R CUP 01 103 0140 11C 1 INNER CONE 01 102 0150 11D 1 INNER CUP 01 103 0130 12 12A 12 SHCS 7 16 20 X 3 0 GR8 01 150 1830 12B 12 LOCKWASHER 7 16 01 166 0340 12C 2 12 PT CBORE CS 1 2 13 X 1 25 GR8 01 150 1460 13 2 PIPE PLUG 3 8 NPT MAGNETIC 01 207 0070 14 14A SHIM 50 004 1521 14B 1 LOCK RING 50 004 1462 14C 1 SPLIT RING MODEL 50 50 004 1452 14D 1 GASKET 90 004 1081 15 1 MOTOR 01 304 0550 MoDel D50 Di...

Page 3: ...CONE 01 102 0140 11B 1 OUTER CUP 01 103 0140 11C 1 INNER CONE 01 102 0150 11D 1 INNER CUP 01 103 0130 12 12A 12 SHCS 7 16 20 X 4 1 2 GR8 01 150 1820 12B 12 LOCKWASHER 7 16 01 166 0340 12C 2 12 PT CBORE CS 1 2 13 X 1 25 GR8 01 150 1460 13 2 PIPE PLUG 3 8 NPT MAGNETIC 01 207 0070 14 14A SHIM 50 004 1521 14B 1 LOCK RING 50 004 1462 14C 1 SPLIT RING MODEL 50 50 004 1452 14D 1 GASKET 90 004 1081 15 1 M...

Page 4: ...emperatures and therefore must be given special consideration The max operating temp must not be exceeded under any circumstances regardless of ambient temperature If your unit was specified shaft up or with a Z option a grease zerk was provided in the base housing For shaft up operation the output bearing will not run in oil and must be grease lubricated Use a lithium based or general purpose bea...

Page 5: ...ess table and unit supported by base press shaft out by applying press load to top end of shaft internal end until it passes through inner shaft bearing 11C Outer shaft bearing 11A and seal 10B will come out of unit attached to shaft 3 Inspect inner and outer bearing cups 11B 11D If cups are damaged remove and replace both bearing cups and cones CAUTION Care should be taken not to injure feet or d...

Page 6: ... 14B onto output shaft 10 Lightly grease a new o ring 10A and install it into o ring groove in base 1 Assemble ring gear 8 to base 1 Re fer back to scribe marks made across external joints of gear drive prior to Disassembly Procedure Line up scribe marks between ring gear and base to give correct hole alignment NOTE Be certain that o ring 10A stays seated in groove during Step 10 11 Install second...