Cleaning and maintenance
Maintenance (expert)
37
2.6.10
Attaching panels
Installing the side covers
Re-install the side covers on the boiler.
Fig. 2-92: Side covers
Mounting the cover on the top
Re-install the cover back on top of the boiler.
Fig. 2-93: Cover
2.6.11
Check boiler doors
Checking the airtightness of the combustion
chamber door
Open the combustion chamber door and then close it
again. When closing, make sure that the door can be
closed fully and with force. The sealing edges of the
door frame must leave an obvious indentation in the
sealing cord of the combustion chamber door.
Fig. 2-94: Check
Leaks can be detected by variations in the colouration
of the sealing cord. If leaks are found, it is usually
sufficient to adjust the hinges and the closing roller
mount. If the hinges cannot be adjusted any further,
the sealing cord must be replaced.
Fig. 2-95: Seal
Also check if the sealing cord is already "hard". To
check, press on the sealing cord with your finger
nail. If it can no longer be pressed, it is "hard" already
and must be replaced.