ETC Installation Guide
ArcSystem Pro Multi-Cell
ArcSystem Pro Multi-Cell
Page 14 of 24
ETC
Complete Installation
1.
Check that all wires are terminated properly and secure in their terminals.
2.
Tuck wiring and WAGO connectors inside wiring compartment. Replace the wiring
compartment cover using the screws set aside previously.
3.
Rotate the fixture so it is roughly focused to its final resting position. This will assist in final
focus procedures.
Installing 100–125 V Emergency Multi-Cell Fixtures
Sense input
Maintained input
100–125 V Pro Four-Cell Round
emergency fixture shown
*Actual cable length
is 2.1 m (7 ft)
ArcSystem 100–125 V multi-cell emergency
systems include Pro Two-Cell, Pro Four-Cell
Square, Pro Four-Cell Linear, Pro Four-Cell
Round, and Pro Eight-Cell models. Arcsystem
100–125 V multi-cell emergency fixtures are
supplied with hard-wired power cables that are
labeled near the strain reliefs for Maintained
Input and Sense Input.
Aside from having multiple power cables, these
fixtures are installed in the same way that
standard multi-cell fixtures are installed.
Depending on the fixture you are installing, see
Installing 100–240 V Multi-Cell Fixtures on
page 8
or
Installing 100–240 V Four-Cell
.
Note:
Fixtures with NEMA 5-15 connectors are
only for use in 100–125 V applications.