__________________________________________________________________________________________________________________
Series GA201-M2
16
LT126 June 2021
3.
Move the Heater by handling ONLY the Pole or the Base Body
. It may take two people to manoeuvre the
Heater safely depending on the size / strength of the person(s).
4. Tip the Heater backwards at an angle to / overtop of the wheels until the Base no longer touches the ground.
Wheel / Roll the heater to the desired location and return base to the ground. Ensure the heater is on level
ground and stable in new location.
5. If the heater is going to be operated at the new location, the “Testing / Commissioning” procedure must be
completed.
Secure the Heater (Optional)
1. Ensure that the Hold Down Brackets are properly installed as described in Installation Step 8.
2. The type of Foundation Fastener required depends on the type of Floor / Ground that the Heater is located
on. Prepare the Floor / Ground as detailed in Table A at all three bracket locations. (Ensure that alignment
with the connecting hole(s) of the Base Bracket is maintained)
Table A: Methods for Securing Heater to Floor / Ground
Floor / Ground Type
Foundation Fastener
Type & Size
Mounting Method
Summary
Floor / Ground
Preparation
Concrete
Concrete Anchor
Ø5/16" x 2 1/2"
Place Anchors into pilot
holes aligned with Base
Brackets -
tap / hammer lightly,
screw fastener into anchor
Drill 3 - Pilot Holes
Pilot hole drill size:
Concrete = 9/16"
Wood Deck
Wood Screw
#10 x 1 1/2"
Secure using Wood
Screws in pilot holes
aligned with Base
Brackets
Drill 3 - Pilot Holes
Pilot hole drill size:
Hardwood = 7/64"
Softwood = 3/32"