CAUTION! 

Use LgY wires for the UPS cables. 

 

 

 

CAUTION! 

Follow  the  phase  rotation  order  when  collecting  the  power 

supply  line.  This applies  to all  components of  the  BYPASS  switchboard 

and the UPS connection.   

 

 

  This UPS has been designed for operation in TN systems 

  The  exact  requirements  are  specified  for  a  local  UPS  switching 

room  located  directly  at  the  device.  Follow  the  applicable  local 

requirements when selecting the wire sizes. 

 

 

CAUTION! 

Only  trained  personnel  may  switch  power  to  the  external 

bypass  system.  Switching  operations  carried  out  against  this  procedure 

may result in damage to the UPS. The external bypass system operation 

is  described  in  a  separate  documentation,  "Instruction  manual  for  the 

external  bypass  system  of  the  POWERLINE  RT  PLUS  6-10  kVA  UPS 

units". 

Summary of Contents for POWERLINE RT PLUS 10 000

Page 1: ......

Page 2: ...020 03 26 16 15 Pomoc Techniczna tel 48 61 6500 400 www ever eu 2 TABLE OF CONTENTS TABLE OF CONTENTS 2 SAFETY REMARKS 3 REQUIREMENTS FOR PREPARATION OF THE POWER SUPPLY AND RECEIVER SYSTEM 3 INSTALLATION GUIDELINES 5 ELECTRICAL SYSTEM 7 TECHNICAL ACCEPTANCE 9 NOTES 9 ...

Page 3: ... and large This require proper transport and handling facilities an adequate number of helpers a forklift truck and properly dimensioned handling routes CAUTION Contact the Technical Service if any damage is found that may affect proper performance of this device B Location CAUTION Selection of the installation site and assurance of proper operating conditions for the device are the user s respons...

Page 4: ...ents of local laws CAUTION Do not connect the PE line to the UPS with copper cable tips The power supply and receiver lines of the UPS shall be isolated It is recommended to specifically mark label the connection outlets to distinguish those of the isolated UPS network from the mains system outlets Connect the UPS to the nearest mains switching board with copper wires in reinforced shields e g coa...

Page 5: ...measurements shall be carried out on the responsibility of the device buyer INSTALLATION GUIDELINES Consider the device weight when choosing the installation site The UPS shall only be operated in rooms where the dust temperature and humidity levels are within the device specifications Appropriate cooling conditions must be ensured for the UPS to work properly For this reason the ventilation openi...

Page 6: ...RAMETERS Output system topology 1P3W Rated output voltage 230 V AC Rated current 26 1 A 43 5 A Minimum output wire size 4 mm2 10 mm2 Output line protection Switch disconnect or Qout 32 A 50 A ENVIRONMENTAL PARAMETERS Heat release under nominal operating conditions 1100 BTU h 1800 BTU h Operating temperature 1 0 40 C Storage temperature 0 40 C Humidity 95 Elevation 1000 m MECHANICAL PARAMETERS Dime...

Page 7: ...POWERLINE RT PLUS 6 10 kVA UPS Installation diagram symbols Fm Fsb Switch fuses Qout Qsb Switch disconnectors PP1 PP2 PP3 Emergency power off EPO push buttons A Connection wires The list of safeguards and wire sizes used in specific locations for specific UPS models is shown in Table 2 Table 2 Safeguards and wire sizes MODEL Fm Fsb Qout Qsb A POWERLINE RT PLUS 6 kVA 32 A gG 32 A gG 32 A 32 A 4 mm2...

Page 8: ...en designed for operation in TN systems The exact requirements are specified for a local UPS switching room located directly at the device Follow the applicable local requirements when selecting the wire sizes CAUTION Only trained personnel may switch power to the external bypass system Switching operations carried out against this procedure may result in damage to the UPS The external bypass syst...

Page 9: ...re the output voltage in the mains operating mode Test the UPS switching from mains to batteries without interruption of the load power supply if possible test at the target load of the UPS circuit Measure the output voltage in the battery operating mode If a bypass is installed train the personnel designated by the buyer in the bypass operation Confirm the completed technical acceptance with the ...