Document No. 1112M001 Revision 1.8 Date: June 2013
31
6.0 Installation Commissioning
The turbine installation on the tower is complete. The electrical
installation is also complete and approved. Safety precautions are in
place ready for the tower to be raised. The electric brake is standard
on the e400n and e400nb. The additional mechanical brake is only
fitted to the e400nb.
►
Complete a visual check on the wind turbine and
ensure that no foreign objects or tools are on or
adjacent to the turbine.
►
Clean the turbine and blades removing any
finger marks.
►
Check all three blades thoroughly for any damage during
installation. Edge damage will increase noise and change the
sound signature of the turbine.
►
Verify that the electrical installation is complete.
►
Verify that the turbine is free to rotate smoothly with no unusual
noises. Now apply the turbine electrical brake switch and engage
the mechanical brake if fitted. Consult the
emergency shutdown procedure.
►
Observing all safety requirements, refer to the
tower manual for the tower raising procedure.
►
Raise the tower as instructed in the tower manual,
completing the tower installation and making
secure.
►
Release all brakes and observe the turbine to run smoothly
with no vibration or unusual mechanical noise.
Congratulations! The installation is now complete !