2.3.
CONFIGURATION OF MANAGEMENT IP CONNECTION
The first step is to configure the management IP connection so that the customer can create
management access to the unit via the user’s Local Area Network. The user can change the
management IP address from the serial port of the frame controller by following the steps below.
1. Remove the panel by unscrewing both knobs on the side.
2. Connect the serial upgrade cable (ribbon cable) provided by Evertz to the 2x3 header at the
front edge of the 7801FC/7800FC.
3. Open a terminal program such as HyperTerminal. Setup the terminal program as shown in
Figure
2-2 : COM Port Settings
4. Power on the unit and allow unit to boot up.
5. After boot up, press
ENTER
and the
Login
screen will appear. Enter login:
customer
and
password:
customer
.
6. After logging in the
Main Menu
will appear in the terminal window as shown in Figure
Figure
2-3 : Main Menu Prompt