Initial Commissioning Procedure 

The following will be checked when commissioning the unit. The method may vary depending on the 
project.  

 

Evinox Energy Commissioning Check-List

 

 

Check if the unit is connected correctly to the hydraulic circuits. Confirm that the 
unit is correctly connected to the electrical supply.  

 

Set the unit into operation by installing firmware, checking if all the components are 
functional.  

 

Confirm the unit performs cooling function. If Evinox ViewSmart Room Controller is 
used this will include ViewSmart functionality check.  

 

Ensure the unit has an ID number, record serial numbers of the control board and 
the heat meter.   

 

 

 

 

Evinox Technical Personnel 
Evinox Technical Personnel who will visit the project during the course of the 
installation and at completion to arrange for final commissioning and calibration, 
do so to assist the contractor and install team to deal with any questions and 
queries. They do not perform the role of quality control or inspector of the 
installation or provide approval for the works carried out.
 

 

Booking Commissioning 
All commissioning must be booked 6 weeks in advance and will be carried out to a 
pre-agreed programme that will be confirmed with the client prior to 
commissioning.  

 

 

Warranty  
Evinox Energy Commissioning is required for warranty validation.  

 

 

 

 

 

 

 

 

 

 

 

 

Summary of Contents for ModuSat SP Cooling Unit

Page 1: ...2551988D ModuSat SP Cooling Unit ModuSat SP Heating Unit Installation Manual...

Page 2: ...NERAL INFORMATION 1 TECHNICAL FEATURES 3 INSTALLATION 7 Water treatment 13 Electrical Connections 15 5 2 1 RJ45 Connections 16 SETTING INTO OPERATION COMISSIONING 19 6 3 1 Pressure independent control...

Page 3: ...2551988D SPH SPC SERVICING AND INSPECTION 23 WARRANTY 24 KIWA CERTIFICATE 26...

Page 4: ...nd operating the ModuSat unit Failure to read and follow the instructions provided within this document may cause a safety hazard or and failure of the equipment Qualified personnel only The Evinox co...

Page 5: ...rks on the unit Qualified personnel Electrical installation must only be carried out by technical personnel In the case of water leak Slowly close the isolation valve at the top of the unit Contact Ev...

Page 6: ...er flow is used to produce secondary heating cooling Apartment heating cooling when the space heating cooling demand is requested by the end user controller the heating cooling operation is started Th...

Page 7: ...r 2 Pressure Independent Control Valve PICV with actuator 3 Heat meter Cooling Secondary Side Circuit 4 Expansion vessel 5 Low pressure switch 6 Safety relief discharge 7 Pressure gauge 8 Dwelling cir...

Page 8: ...Water Primary circuit max pressure 16 bar Optional Primary minimum differential pressure 50 kPa 0 5 bar may vary depending on the required output Primary maximum differential pressure 400 kPa 4 bar m...

Page 9: ...r access and servicing Top 190 mm should be allowed for the flushing bypass kit on the top of the unit with 3 4 connections and 250 mm for the units with 1 connections Front 700 mm Side 50 mm Bottom S...

Page 10: ...tion site or the property Lifting Take care when lifting this appliance It is recommended that at least two people perform the lifting Leave caps over the connections Ensure that the protective cover...

Page 11: ...ed to be wall mounted with the typical primary and secondary connections as shown below The Evinox Energy flushing by pass valve kit should be installed prior to connecting the unit and the valves lef...

Page 12: ...ng the ModuSat SPC Pre Installation Rig on the wall fixing bracket Then slide down by 15mm and across to the right by 30mm as indicated in diagram STEP2 Fit the Evinox Energy Flushing Bypass Valve Kit...

Page 13: ...ystem The kit includes an H shape by pass with inbuilt isolation valve 1 strainer and 3 isolation valves Evinox FLUSH KIT C01 SS for ModuSat SPC Evinox FLUSH KIT SP1 SS for ModuSat SPH Close valves Be...

Page 14: ...ting the ModuSat heat interface unit ensure that all the connections are tightened to avoid any leaks First fill of the HIU Clean and flush the system before connecting the unit Filling the system sho...

Page 15: ...ating or cooling system The ModuSat unit is fitted with a manometer gauge that is mounted in the front panel This gauge reading should be used when filling the secondary circuit An external filling lo...

Page 16: ...to BSRIA Application Guide BG29 2012 BS7593 2006 Requirements of Thames Water Utilities The Water Industry Act 1991 Section 119 HSE The Control of Legionellosis 1991 HSC Approved Code of Practice and...

Page 17: ...t consultants that the chemicals used and cleaning method statement complies with the requirements set out in this section Evinox Energy do not take responsibility for approving inhibitors used for do...

Page 18: ...anty Evinox Energy cannot accept any responsibility for incorrect wiring The ModuSat wiring board is located within the ModuSat itself under a removable metal cover To access the connection board the...

Page 19: ...ol board is located next to the connection board on your right hand side The control board cover must not be removed Doing so may invalidate the warranty Connection Terminations Evinox Energy strongly...

Page 20: ...17 2551988C ModuSat Connection Board Please Note When connecting external valves or pumps to the ModuSat control board it must be ensured that each connection does not exceed 1amp 220 240V AC...

Page 21: ...ING WITH NOTES AT THE END OF THIS MANUAL SmartTalk system wiring Typical Modbus system architecture SEE STD MOD 2013 BUS 1 E DRAWING WITH NOTES AT THE END OF THIS MANUAL Typical TCP IP system architec...

Page 22: ...ort to Evinox Energy Pre commissioning checklist Pre requisite of Commissioning Check 1 Primary network and plant room fully operational and complete including water treatment in line with these instr...

Page 23: ...nction will run for a pre set period of approximately 45minutes Rocker Switch Please note The rocker switch below the commissioning push button is the Pump Manual Override This should NOT be operated...

Page 24: ...ks red green Pump in function but stopped Pump restarts by itself after the fault is disappeared 1 Low voltage U 160 V or High voltage 253 V 1 Check voltage supply 195 V U 253 V 2 Module overheating t...

Page 25: ...k 4 Ensure the unit has an ID number record serial numbers of the control board and the heat meter Evinox Technical Personnel Evinox Technical Personnel who will visit the project during the course of...

Page 26: ...Visual inspection of primary isolation valves 3 Strainer valves clean where accessible 4 Primary differential pressure above required minimum 5 Thermal insulation intact 6 Secondary heating cooling s...

Page 27: ...strictly limited to the supply free of charge of parts acknowledged as being defective after inspection by our technical department Any costs arising from this inspection will be charged if the part...

Page 28: ...installation and servicing manuals to ensure long life reliability and efficiency Exclusions to the Warranty The following are not covered by the warranty Electric degradation of parts resulting from...

Page 29: ...26 2551988C KIWA CERTIFICATE...

Page 30: ...G PRODUCT DEVELOPMENT NOTES TYPICAL WIRING CONNECTION ARRANGEMENT WITH TWO ROOM CONTROLLERS AK SEP 2018 N T S PL STD MOD BMS Electric wiring of MODUSAT and VIEWSMART The MODUSAT connection board is in...

Page 31: ...ACTERISTICS OF ITS EQUIPMENT WITHOUT PRIOR NOTICE AS PART OF ITS CONTINUING PRODUCT DEVELOPMENT NOTES Energy MODUSAT SmartTalk DATA LOGGER AND SUPPLY UNIT BUS PRINCIPLE SYSTEM ARCHITECTURE BJW AUGUST...

Page 32: ...TIONAL NETWORK SWITCH INSIDE APARTMENT OPTIONAL MODUSAT UNIT MODUSAT CONTROL BOARD MODUSAT UNIT MODUSAT CONTROL BOARD MODUSAT UNIT MODUSAT CONTROL BOARD MODUSAT UNIT MODUSAT CONTROL BOARD NETWORK SWIT...

Reviews: