6 Packet Path Test
This test verifies the internal paths to test the Ethernet interfaces in the system, including between the
front panel switch, HSBs, processors, and more.
When you start the test, you see this message:
Test Begin: Packet Path Test (excluding modules)
After the test completes successfully, you see this message:
Test Complete: Packet Path Test (excluding modules): PASSED
7 Power Supply Test
This test reports status about the power supplies installed in the system, including information about the
supply manufacturer, voltage, and current and temperature measurements.
When you start the test, you see this message:
Test Begin: Power supply Test
After the test completes successfully, you see this message:
Test Complete: Power supply Test: PASSED
8 Fan Test
This test reports status about the fan trays installed in the system.
When you start the test, you see this message:
Test Begin: Fan Test
After the test completes successfully, you see this message:
Test Complete: Fan Test: PASSED
9 Config Module Test
This test verifies the internal paths to test the configuration modules installed in the system.
When you start the test, you see this message:
Test Begin: Config Module Test
After the test completes successfully, you see this message:
Test Begin: Config Module Test
Field Testing F5 Hardware: iSeries Platforms
15
Summary of Contents for iSeries
Page 1: ...Field Testing F5 Hardware iSeries Platforms MAN 0638 02 ...
Page 2: ......
Page 4: ...Table of Contents 4 ...
Page 6: ...The End User Diagnostic EUD 6 ...
Page 18: ...EUD Tests 18 ...
Page 22: ...Index 22 ...