VIGILO
VIGILO
6
!
!
1,0 m - str
oke 500
1,2 m - str
oke 600
1,3 m - str
oke 800
Cover with
about 30 cm
of concrete
Spirit level
30 cm
15 cm
12 cm
depth piping
centre
15 cm
loose pebble
drainage layer
170
410
410 mm
Ø 60
Ø 275
FRONT SIDE
Soakaway pebbles
Possible
submersed
pump
87 cm
FRONT SIDE
87 cm
43,5 cm
43,5 cm
23 cm
23 cm
English
fully retractable oil-hydraulic bollard
Pic. 4
Pic. 5
850 - str
oke 500 mm
960 - str
oke 600 mm
1.140 - str
oke 800 mm
ARRANGING THE HOUSING
Check soil natural permeability: 50 liters of water must be
able to soak away in not longer than 30/40 minutes.
Otherwise provide a pipe to allow rain water to flow either
into the sewage system or a sump well equipped with a
submersed pump.
IMPORTANT: once the housing has been positioned and installation completed, it is important for the top edge
to be level with the ground.
Housing
Concrete
cast
Piping Ø 5 cm
for passage