Installation & User Manual Falcon Electric, Inc.
FN2 Series OM480051 Rev.: E
23
Start-up Procedure
AC Start
1. Verify input terminals are wired properly for 208V or 240V Utility Input Power.
a. Verify all grounds are wired properly.
2. Turn on the input circuit breaker to start up the UPS. Green LEDs
and
show
that the Utility and Bypass inputs are normal. UPSs with parallel function enabled will
display figure A1, then figure A2, and then figure B. Otherwise, the LCD will display
figure A1 directly followed by figure B.
A1
A2
B
3. The UPS is now in Bypass Mode. It will proceed to self-test automatically. If no abnormal
message appears then the pre-startup of the UPS was successful, and the charger
starts to charge the batteries.
4. Press the UPS On button for approximately three seconds. The buzzer sounds twice
and the LCD display changes from figure B to figure C.
C
Summary of Contents for FN2-4.5K-2TXI
Page 2: ......
Page 12: ...Installation User Manual Falcon Electric Inc FN2 Series OM480051 Rev E 12 Accessories Kit...
Page 26: ...Installation User Manual Falcon Electric Inc FN2 Series OM480051 Rev E 26 I1 J K L M N...
Page 27: ...Installation User Manual Falcon Electric Inc FN2 Series OM480051 Rev E 27 O O1 P O2...
Page 29: ...Installation User Manual Falcon Electric Inc FN2 Series OM480051 Rev E 29 S2 T U V1 V2 V3...
Page 39: ...Installation User Manual Falcon Electric Inc FN2 Series OM480051 Rev E 39...