Traffic-Control
EN
Possible use
X 1
X 2
X 3
Sensor at
input
E1
E2
E3
activates
K
K
K
at output
A1
A2
A3
for the
period of
Poti 1
1 s
15 s
Possible use
Level crossing
Sensor at
input
E5 (Train’s contact
Beginning)
E6 (Train’s con-
tact End)
E7
E8
activates
HST
BL 1 BL 2
ST 2
ST 3
at output
A6
A4
A5
A7
A8
for the
period of
Poti 2
Table 19: Program 14
X
Set the DIP as required, see Fig. 19.
X
Connect the components, see Table 19.
X
If necessary, set the desired period using the potentiometers.
Program 15
Fig. 20: DIP configuration Program 15
This program allow to represent a complete level crossing. Unlike program
14 you will have here the possibility of allowing up to three vehicles to wait
at the level crossing one behind the other.
Inputs E3 to E8 and outputs A2 to A8 form together that level crossing. You
will set the delay times necessary for the stop sections provided behind to
be cleared using Poti 1 for outputs A5 and A6, while using Poti 2 for out-
puts A7 and A8. Please also pay attention to the description of Program 14.