4
Please follow all applicable codes when installing this unit
1. Equipment should be hung at its proper elevation by using
temporary fixtures that can be removed after vibration
hangers are installed. (Vibration isolation mounts provided
by others)
2. Hanger may be fastened directly to the structure or
somewhere between suspended unit (be sure not to
over tighten the neoprene element).
3. Install hangers.
4. Turn nuts on rod assembly clockwise one complete turn
on each hanger. Repeat this procedure until temporary
hanging fixtures are loose and load of piping or equipment is
suspended completely on the vibration hangers.
5. Remove temporary hanger fixtures and level piping or
equipment by taking additional turns on the spring/top
hanger rod nut – clockwise to raise, counterclockwise to
lower as required.
6. If equipping fan with isolators (FC Clamps), they should
be attached at this time.
7. See wiring section to complete installation.
Mounting Illustration 1
Vibratio n
Mount
Detail
Please follow all applicable codes when installing this unit
1. Install wood supports to structure for fan mounting.
2. If equipping with vibration mounts, attach to supports.
3. Attach fan to vibration mounts, supplied by others (be sure
not to over tighten the neoprene element).
4. If equipping fan with isolators (FC Clamps), they should be
attached at this time.
5. See wiring section to complete installation.
Mounting Illustration 2
Please follow all applicable codes when installing this unit
1. Create/Install angle wood supports to structure for fan mounting.
2. If equipping with vibration mounts, attach to supports.
3. Attach fan to vibration mounts, supplied by others (be sure
not to overtighten the neoprene element).
4. If equipping fan with isolators (FC Clamps), they should be
attached at this time.
5. See wiring section to complete installation.
Mounting Illustration 3
Mounting
Bracket
Vibration
Mounts
Fan
Bracket
Detail
Please note: Vibration Mounts and Hardware are not supplied with fan. fc clamps are sold separately.