Page 2 of 4
©2015 Hubbell Incorporated | SureFit™ Full-Tension Aluminum Automatic Splices
1. Place the grips of the hoist or come-along as far apart as possible. This creates slack in the
conductor to simplify insertion.
2. Do
NOT
remove color coded funnel guides from ends of splice.
3. Check the conductor size and type stamped at the center of the splice (center stop location) to
ensure correct size for application. See Figure 1 for internal components.
4. Straighten the conductor to remove any coil or curvature. Be sure that the conductor is as straight
as possible and that the strands are in lay before proceeding with installation.
5. If shortening is necessary, determine where the cut point on the conductor will be, then tape the
conductor next to the cut point. Cut the conductor squarely to make certain that all strands are
even and in lay.
6. File the burrs from the conductor end.
REMOVE TAPE.
7. Measure the portion of the conductor that will be inserted from end of funnel guide to center
stop, and
CLEAN IT WITH A WIRE BRUSH
, regardless of the conductor condition.
8. Insert the conductor smoothly in one motion
WITHOUT TWISTING
until the funnel guide is
released. Do
NOT
attempt reinsertion if the funnel guide remains fully seated. See Figures 2 – 3.
9. After both ends have been inserted, pull down firmly on the splice to obtain an initial jaw set on
the conductor.
10. Apply tension on span by loosening the hoist or come-along. Move to center of span and pull
down on the conductor, then remove hoist or come-along.
DANGER
NOTICE
!
!
!
!
!
!
!
!
!
!
!
!
DESIGNED for full tension applications.
Do NOT use on slack span applications.
Do NOT remove hoist or come-along without both funnels being released.
A MINIMUM installation tension of 15% of the conductor RBS is recommended for best electrical
performance.
Do NOT reuse SureFit
TM
aluminum automatic splice.
Keep SureFit
TM
aluminum automatic splice inside bag until installation time.
Instructions provided for reference only and should not replace utility training.
Do NOT hit the SureFit
TM
aluminum automatic splice with any tool or other object to set the jaws.
Contact Hubbell Power Systems, Inc. for application questions.
CONDUCTOR MUST BE CLEAN (WIRE BRUSHED), STRAIGHT, IN LAY AND FREE OF BURRS TO
ENSURE PROPER INSTALLATION AND LONG TERM PERFORMANCE.