Install Mid-Rafter Vertical Headers
Mid-Rafter Vertical Headers are fixed sections runs of 2"x2" tubing installed just inside the rafter legs at every
mid-rafter with a support chord assembly, or every 12'. Intermediate monofilament clips, panel fixation & sealing
components, and drive components are all attached to the mid-rafter headers--horizontal and vertical.
ASSEMBLE AND INSTALL MID-RAFTER VERTICAL HEADERS
Install provided vertical header tubing as shown as every rafter with a support chord assembly.