96
Revision date: 12.02.16
Black-out System Installation
SPLICE DRIVE SHAFT
1. Position all four drive pipe runs in the CLOSED position. In this position, the open bay--or the bay without the drive
pipes--will be the bay at the end wall to which the 113650 wire tensioners are attached. Verify that 2" of drive pipe
extends into the open bay. See diagrams below.
2. Once in place, the four rack arms should be sitting
in the rack drives in the same position across the
power rafter. If not, adjust as needed so that all four
rack arms are identically sitting in the four rack drives.
Temporarily secure drive pipes in place.
3. Return to the drive shaft and motor couplers. Field
drill through-holes and splice all coupler connections
XVLQJ[EROWV)$*%ÀDWZDVKHUV
(FAME07B), and 5/16" lock nuts (FALF37B).
IMPORTANT:
When splicing drive
shaft
components,
verify that the drive
pipe
components DO NOT MOVE
OR SHIFT from the position they have just been set.
A
A
B
B
Push all drive
pipes to this end.
Drive Pipe
Drive Pipe
Telescoping Purlin
Telescoping Purlin
Verify drive pipes
extend into open
bays 2".
2"
POWER RAFTER
112571 coupler
OR
111675 coupler
(2x) 5/16" x 2" bolts (FAG334B)
(4x) 5/16" washers (FAME07B)
(2x) 5/16" lock nuts (FALF37B)
Drive Shaft
*some framing and
drive components
removed for clarity