310.7 Drum Kit/Slide Gate
Figure 310.3
(GS6 shown)
3/8-16 THREAD
CUTTER SCREW
"MATCH LINE"
LABEL
~
~
UPPER SIDE
PANEL
LOWER SIDE
PANEL
LIFTING LUG
FULL MODULE
(4 CARTRIDGES)
HALF MODULE
(2 CARTRIDGES)
ROPE CAULK
Clean and apply rope caulk to the top
surface of the slide gate flange. Bolt
the slide gate to the hopper
discharge flange; making sure that
the slide gate is oriented so that
there is no interference when the
handle is pulled out. Fasten one end
of the flexible hose to the slide gate
collar with a hose clamp. Slip the
other end of the flexible hose over
the collar of the drum lid and fasten
with a hose clamp. If you have a
positive pressure drum kit, slip the
drum ring over the top of the drum.
Slide the ring down far enough so
that when the (4) clamps are
secured, the drum lid gasket seals
tightly against the top surface of the
drum. Tighten the drum ring screw. If
you have a negative pressure drum
kit, place the drum lid on top of the
drum with the gasket surface
contacting the top surface of the
drum. – Figure 310.7.
310.8 Platform/Ladder
If equipped, lift the platform assembly
into position and install using the
hardware provided. Lift and install
the access ladder using the
hardware provided. Refer to the
Platform/Ladder assembly drawing
and General Dimensions drawing for specific instructions. It may be necessary to cut
the ladder to the exact length.
Note: The installing contractor must brace the ladder properly.
13
Drum lid
Hose clamp
Flexible hose
55 GAL
Drum
55 GAL
Drum
Attach to discharge
flange on hopper.
Hose clamp
Slide gate
Hose clamp
Flexible hose
Hose clamp
Drum lid
Slide gate
Drum latch ring
Negative
Pressure
Drum kit
Positive
Pressure
Drum kit
Figure 310.7
Summary of Contents for Gold GS10
Page 75: ...75 ...