4000 Series
Page
8
of
41
3460006-17_serial series 5000000
4.0 Setup/ Installation:
1.
Note: The receptacle for this unit must be positioned such that this unit can be rolled on its
casters to achieve the following receptacle spacing: At least a 3 foot clearance in front of
the receptacle, with a 30” wide working space, and headroom at least the height of the
equipment.
2.
Roll the unit into place near the required power connection. Allow for 6” (15.3 cm) of
clearance from the back and sides for air flow and door opening clearance. If lifting the unit,
place lift forks under center of enclosure.
3.
Remove the foam wrapped (2) shelves (10) shelf clips and the evaporator pan from the unit
interior and unwrap.
4.
Remove the (4) spring feet from the packaging and install on the evaporator (4) bottom
projections of the evaporator pan (small end first). (see photo below)
5.
Condensate drain p-trap tubing.
Spring Feet
End to be inserted into
cabinet drain connector.
See next instruction
Condensate outlet