34
!
"
!
Panel Saw
K3 basic/K3 winner/K3 e-classic
Setup and installation
1.
Transport the machine to the installation site as in-
structed in the „Transport“ chapter and the enclosed
transport or installation instructions.
2.
Position the machine with the aid of a spirit level to
ensure that the machine functions precisely and oper-
ates smoothly.
Compensate for uneven floors with the „adjusting
screws“.
!
Spirit level
"
Adjusting screws
Fig. 7-2: Positioning the machine
Fig. 7-3: Floor mounting
3.
If necessary, the machine can be bolted down to the
floor with the transport brackets.
!
Transport brackets
Fig. 7-4: Transport locking device Sliding table
4.
Before the machine operates for the first time, re-
move, from both sides, the wedges between the base
and sliding table.
5.
Remove the oxidation protective layer from all blank
machine parts.