background image

 

5  

PROCEDURE: 

• 

Cover the hydro- insulated foundation with a thermal-
insulation layer, then cover this layer with a 4 cm layer of 
concrete. 

• 

Allow the concrete to set fully. 

• 

Clean the concrete area, remove any sharp objects and 

coat it using a suitable penetrating solution. 

• 

Place the heating cable in an open- looping pattern in 

accordance with the required output. 

• 

Fix the heating cable (e.g., using Grufast fastening strips) 

so that it cannot move during further concreting. 

• 

In humid spaces, connect the protective braiding of the 

cable to the protective grounding connection for the room. 

• 

Measure the resistance of the heating circuit and the 
insulation resistance and record the measured values in the 
certificate of warranty. 

• 

Cover the cable with a concrete layer up to the required 

height. After concreting is finished, measure the resistance 
values again and record them in the certificate of warranty. 

• 

Wait at least 28 days after installation before putting the 
mat into operation, so that the concrete will be set fully. 

• 

Materials used in finishing the floor surface (glue for tiles, 

carpet, parquets, etc.) must be approved by their respective 
manufacturers for use on floors under thermal stress.

 

 

POSTUP — poloakumulační systém 

• 

Na hydroizolovaný podklad položte tepelnou izolaci, na 
izolaci vytvořte 4cm vrstvu betonu. 

• 

Beton nechte vyzrát. 

• 

Betonovou vrstvu očistěte a zbavte ostrých předmětů a 
natřete penetrační nátěrem.

 

• 

Rozviňte topný kabel ve tvaru meandru, dle požadovaného 
výkonu. 

• 

Topný kabel fixujte tak, aby se při další betonáži nemohl 
pohnout, např. páskou Grufast. 

• 

Ve vlhkých prostorech spojte ochranné opletení kabelu s 
ochranným pospojováním místnosti. 

• 

Proveďte proměření odporu topného okruhu a izolačního 
odporu zapište do Záručního listu. 

• 

Kabel zalijte vrstvou betonu do požadované výšky, po 
skončení betonářských prací opět proveďte měření a zápis 
do Záručního listu. 

• 

Rohož uveďte do chodu nejdříve po 28 dnech, po úplném 
vyzrání betonu. 

• 

Materiály dále používané pro zušlechtění povrchu podlahy 
(lepidlo na dlažbu, koberec, parkety apod.) musí mít dopo-
ručení od výrobce, že jsou určeny pro tepelně namáhané 
podlahy. 

Semi- accumulating system / 

Poloakumulační systém 

 

1) Base  / Podklad 
2) Thermal insuletion, 80mm Tepelná izolace 80mm 
3) Reinforcing steel grid / Armovací ocelová síť 
4) Ecofloor heating cable / Topný kabel Ecofloor 
5) Accumulating concrete layer, 80- 100 mm / Betono-

vá akumulační vrstva 80—100mm 

6) Installation pipe with a floor probe / Instalační 

trubka s podlahovou sondou 

7) Floor finish / Nášlapná vrstva 

c) Regulation 

• 

For regulation, use one of FENIX’s available thermostats. 

• 

For floors where exceeding the hygienic limit of 27°C 

is not anticipated, or for floors in rooms occupied for 
only short intervals (bathroom, lavatory, corridor) with 
surface area output of up to 160 W/m

2

, it is optional 

to use the thermostat’s limiting floor probe. For all 
other applications, the thermostat must be equipped 
with a floor probe with the maximum temperature set 
to 35°C. 

• 

For semi- accumulating floor heating, a thermostat with a 

floor probe is required.

 

 

c) Regulace 

• 

Pro regulaci použijte termostat z aktuální nabídky firmy 
FENIX. 

• 

U podlah, kde se nepředpokládá překročení hygienické 
hranice 27 °C nebo se jedná o krátkodobě obývané 
místnosti (koupelna, WC, chodba) s plošným příkonem do 
160 W/m

2

 

není podmínkou limitující podlahová sonda 

termostatu. U všech ostatních aplikací musí být termostat 
vybaven podlahovou sondou s max. nastavením 35 °C. 

• 

U poloakumulačního podlahové vytápění je nezbytný regulátor 
s podlahovou sondou.  

Summary of Contents for MPSV 15

Page 1: ...odavatele stavby o um st n topn jednotky a o rizic ch z toho vypl vaj c ch Plocha mus b t po cel m obvodu odd lena od svisl ch konstrukc dilata n sp rou polystyren mirelon apod tl do 10mm The heating...

Page 2: ...ctures by an expansion joint polystyrene Mirelon etc up to 10 mm wide In case that cables are laid in an area larger than 20 m2 or with a diagonal greater than 7 m it is necessary to account for expan...

Page 3: ...ing system The installed output should correspond to a multiple of 1 1 to 1 3 times the calculated thermal loss due to the maximum recommended outputs see table below An additional heating device must...

Page 4: ...floor probe Instala n trubka s podlaho vou sondou 7 Finish floor N lapn vrstva b Installation system with moderate accumulation of heat INSTALLATION INTO CONCRETE self levelling screed Firstly read G...

Page 5: ...ojov n m m stnosti Prove te prom en odporu topn ho okruhu a izola n ho odporu zapi te do Z ru n ho listu Kabel zalijte vrstvou betonu do po adovan v ky po skon en beton sk ch prac op t prove te m en a...

Page 6: ...ch Prvn den nastavit teplotu podlahy shodnou s teplotou v m stnosti maxim ln 18 C N sleduj c dny zvy ovat teplotu podlahy postupn o 2 C den a na 28 C Teplotu podlahy udr ovat na teplot 28 C po dobu t...

Page 7: ...n mind that valves connections and flanges have greater thermal loss Therefore it is necessary to wind the cable in these parts in a closely spaced manner b Mont Topn kabely a senzor se mus k potrub p...

Page 8: ...ilable at the website http www fenixgroup cz 4 Z ruka reklamace Dodavatel kabelov ch okruh ECOFLOOR poskytuje z ruku na jej funk nost po dobu 24 m s c ode dne instalace potvrzen na z ru n m list insta...

Reviews: