11
VF5
AUTOMATIC DOORS FOR LIFTS
Switch off the VF control before connecting the open and close command cables. Do not
mix the voltages from the lift controller with the internal ones in the VF control (9: 12 V
and 11: 0 V).
B Put the potentiometers to the minimum.
- Close Speed (52).
- Open Speed (53).
- Safety (54).
C Test the door.
- Check from the landing door side.
- Press the «TEST» button and establish the potentiometers (open speed, close speed and the
safety force) in order to get the required adjustment.
Information:
The VF parameters could be adjusted with the Fermator programming tool.
Remove the photocell wiring from any place where there are “electric noises” such as motors,
supplies wiring, etc.
A
Verify that there is an emitter and a receiver (E mark and R mark on the capsules) connected to the
correct cable (emitter to the yellow cable and receiver to the green one).
B
Connect the photocell (on the operator).
Even if you will not install the photocell, make the learning of the photocell to avoid that
the photocell relay is active by no reason. Once the photocell is verified, it is possible to
disconnect it and the VF control will detect that is not connected anymore.
C
Put the capsules face to face at a minimum distance of 50 cm, make the autoadjusment process
without hitting the capsules, once done, make a open and a close movement, and then block the
photocell with the hand during the close movement to check that the Photocell relay is active every
time the hand is in the middle of the infrared beam.
NORMAL REGULATION WITH THE LIFT CONTROLLER
TEST OF THE PHOTOCELL
12
11
10
9
8
EXTERNAL VOLTAGE INPUTS
Open
Close
Voltage
12 V DC...60 V DC,
100 V AC... 230 V AC.
OPEN
Voltage
12 V DC...60 V DC,
100 V AC... 230 V AC.
CLOSE
12
11
10
9
8
INTERNAL VOLTAGE INPUTS
Open
Close
OPEN
CLOSE