The VF may be programmed using the DIP switches on the front of the unit. If any 

change is made to any of the above switch selections, the main supply of the VF 5 

unit MUST be switched OFF and ON again to read the new programming. 
 The switches functions are:

1 & 2 Inputs.
ON:

 1 Input.

The door control unit will be controlled by a single input. Any voltage between 12 V DC to 

60 V DC or door remains opened. When it activates the door close. Open input is not used.

OFF:

 2 Inputs.

The door control module will be controlled by two independent inputs. Any voltage bet-

ween 12 V DC to 60 V DC or 100 V AC to 230 V AC applied between terminals 8 & 10 will 

cause the doors to close. And between terminals 10 & 12 will cause the doors to open. 

In the absence of a signal, the doors will remain static. If both inputs are applied then the 

open signal has priority.

Automatic/ Semiautomatic.

 ON:

 Automatic.

Operators with skate (automatic landing). In this case a special movement is made for 
locking and unlocking the skate.   

 

OFF: 

Semiautomatic.

Operators without skate (Semiautomatic landing door)

Rotation sense.
ON:

 Lock at the picture:

-Skate fixed on the top side of the belt  

  and the motor on the right side.
-Skate fixed on the bottom side of the 

  belt and the motor on the left side. 

OFF:

Lock at the picture:

-Skate fixed on the bottom side of the 

  belt and the motor on the right side.
-Skate fixed on the top side of the belt 

  and the motor on the left side.

Com

0 V

12 V

8

9

10

11

12

1 INPUTS

Close

Open

Without Voltage

 

0 V

OPEN

With Voltage

 

12 V DC...250 V DC,

100 V AC..230 V AC

CLOSE

Com

0 V

12 V

8

9

10

11

12

2 INPUTS

Close

Open

Voltage

 

12 V DC...60 V DC,

100 V AC...230 V AC

CLOSE

Voltage

 

12 V DC...250 V DC,

100 V AC...230 V AC

OPEN

Summary of Contents for VCI-VF5A.CD0 Series

Page 1: ...ENG Assembly manual Automatic horizontal sliding car door Component VF5 Electronic Module AUTOMATIC DOORS FOR LIFTS MAN MMCAENGV5TC 10 2017...

Page 2: ...lose 100 230V AC DC PM ASYNC 13 Derecha Right QCI VF5A CD0EE ENCODER 12 V COM CERRAR LENTO SLOW CLOSE REABRIR RE OPEN SE AL DE PISO FLOOR LEVEL ENTRADAS PRIORITARIAS PRIORITY INPUTS FOTOC LULA PHOTOCE...

Page 3: ...s to open In the absence of a signal the doors will remain static If both inputs are applied then the open signal has priority 2 Automatic Semiautomatic ON Automatic Operators with skate automatic lan...

Page 4: ...from the supply It is important that the Door Operator Module has a GOOD EARTH CONNECTION The circuit can work with external voltage inputs or internal voltage input voltage free contact 8 Close signa...

Page 5: ...trol is the optional incorporation of the Fermator photocell It is composed by a emitter and receptor infrared 21 Re open This signal is used for installing the cabin door switch or an external barrie...

Page 6: ...0 41 Obstruction Led indicator and relay activated when an obstacle is detected that stops the doors from closing The signal will reset when the doors reach the opened or closed position Note In USA m...

Page 7: ...rocessor will calculate the acceleration and deceleration ramps and the braking torque required to give the optimum control of the doors 52 Close speed The door closing speed can be independently adju...

Page 8: ...te of the photocell Priorities 1 21 23 Reopening 2 Obstacle 3 25 23 Slow Closing 4 17 20 Photocell 5 8 Close SLAVE 2 INPUTS Configuration 1 ON 2 Inputs 2 Depends on type of door 3 Depends on type of d...

Page 9: ...with this configuration then there is a mechanical problem or electric motor or controller not supplied 6 Place the door in a middle position in order to see the starting movement 7 Switch on the VF...

Page 10: ...the encoder if nothing solves it The door opens instead of close Verify the DIP switch 3 position Reverse 2 phases of the motor connection 56 The door makes the learning phase correctly but the skate...

Page 11: ...e correct cable emitter to the yellow cable and receiver to the green one B Connect the photocell on the operator Even if you will not install the photocell make the learning of the photocell to avoid...

Page 12: ...is the clear entrance of any controller that has never been adjusted Therefore an autoadjustment is required check the autoadjustment process The door opens but doesn t close Check if the photocell L...

Page 13: ...of the motor and consequently the encoder is sending a wrong information Adjust the belt tension and make the autoadjustment again The system gets power but doesn t work and the led ON is off Check i...

Page 14: ...oltage supply 230 V Power 250 W Nominal torque 1 5 N m Nominal speed 900 RPM Thermic class F 155 C MOTOR PM Synchronous permanent magnet 10 pole Voltage supply 88 V Power 63 W Nominal torque 1 N m Nom...

Page 15: ...ioned below conform with the following E U council directives European Directive 2014 30 EU on Eelectromagnetic Compatibility EMC in accordance with the Product family standard for lifts escalators an...

Page 16: ...ge produced in the equipment described in this manual and associated installation if the instructions given have not been followed TECNOLAMA reserves the rights to modify the products specifications o...

Reviews: