MY Series (10kVA-40kVA) UPS
User Manual
3 Installation
31
Figure3-9
30/30S/40/40S installation hole size of pedestal (top view)
Bolt
Spring gasket
Flat gasket
Expansion tube
1. Drill holes on the installation ground by hammer drill.
2. Tighten the expansion bolts mildly, and put it to the
hole vertically, and then knock the expansion bolt by
rubber hammer till all the expansion tube into the hole.
3. Pre tighten the expansion bolt.
4.Screw out the bolt , take down the spring gasket and
flat gasket.
Figure3-10
Expansion bolt structure and installation
The exposed height of expansion bolt must be within 50mm.
Step 3
Move the UPS above the holes, pre-lock the supporting plate (not fully locked, leave one-third to
two-thirds of the screws). Move and align the bottom installation hole of the supporting plate with the
expansion bolt. Install the flat gasket (Φ8), spring gasket (Φ8) and screw the bolts. Tighten the UPS
and the six unlocked screws of supporting plate. Then screw down the supporting feet anticlockwise
of the UPS to parallel with ground (just for 30/30S/40/40S).
During moving the UPS, please move the device stably and avoid device tilting.