FIREPOWER 160S
INSTALLATION
Installation 3-10
Manual 0-5369
5. Once leak testing has been performed and there
are no leaks in the system, slowly open the
cylinder valve and proceed.
!
WARNING
If a leak has been detected anywhere in the
system, dis continue use and have the system
repaired. DO NOT use leaking equipment. Do
not attempt to repair a leaking system while
the system is under pressure.
3.10 When You Finish Using the
Flowmeter/Regulator
1. Close the cylinder valve.
2. Open the valve on the downstream equipment.
This drains all pressure from the system.
3. Close the valve on the downstream equipment.
4. Turn the adjusting screw counterclockwise to
release the ten sion on the adjusting spring.
5. Check the gauges after a few minutes for
verification that the cylinder valve is closed
completely.
3.11 Storage of the Flowmeter/Regulator
When the Flowmeter/Regulator is not in use and has
been removed from the cylinder, it should be stored in an
area where it will be pro tected from dust, oil, and grease.
The inlet and outlet should be capped to protect against
internal contamination and prevent insects from nesting.