2. Installation
The front panel of the FPC-2V2 should be removed by loosening the two M4 fixing screws
holding it in place and should be put in a safe place along with the screws for refitting
later.
The back box can then be used to mark the fixing position holes in the required place.
The box should be mounted with screws of a minimum 4mm diameter in all four fixing
positions.
Figure 1- Fixing centres of mounting enclosure
(Not to Scale)
The back box has several 20mm knockouts in the top and bottom. Remove the
knockouts required and fit 20mm cable glands and the required cables.
Figure 2 – Knockouts
(Not to Scale)
If additional cable entries or cable entries in different positions to those provided are
required, these cable entries should be drilled at this stage and any swarf or debris
removed from the enclosure.
Use proper 20mm glands and seal all unused openings properly
21mm diameter knockouts