Installation
3
♦
Notes:
•
To assemble the FSC, you will need a cleared workspace approximately 10'x10'.
•
All views mentioned for the assembly of the FSC are from the perspective of the customer
facing the standing machine.
•
All bolts are inserted from left-to-right, or from front-to-back.
2.
Terminology for Set-Up
The Vertical Track Assembly has been assembled for you. Familiarize yourself with the main
parts of the pre-assembled unit.
Vertical Track Assembly
– the plane that the blade moves along.
Cutting Head
– holds the cutting tool and moves along the Vertical Track Assembly.
3.
Pre-Assembly
In order to make your assembly of the FSC as
easy as possible, organize your workspace so
you have all the necessary tools and parts at
hand.
1.
Match up the screws and bolts with the correct number of washers and their nuts
(see
Hardware List, Section 1.-B. on page 2 for detailed list)
.
2.
Arrange the tools needed to complete the assembly.
a. 3mm, 4mm, 5mm, and 6mm Hex Key
a. 8mm, 10mm, 13mm, and (2) 17mm Wrenches
b. 2-3 boxes approximately the same height
c. Flat Head Screwdriver
d. Drill (wall-mounted unit only)
e. Carpenter’s Level (wall-mounted unit only)
At the beginning of each section there is a “Parts Needed” list. Have these items close at hand
as they will be needed in the assembly of that section.
Cutting
Head
Vertical
Track
Assembly