IJ PUMP OPERATION AND MAINTENANCE MANUAL
6-15
BO2660-01
number 1, and the numbering continues consecutively to the discharge stage. Therefore, in order to
maintain dynamic balance of the rotor, it is very important to ensure that each impeller, split ring, and
key are matched by stage number during disassembly and assembly.
6.4.6.2.3 Vertical Disassembly
The vertical disassembly procedure assumes that the coupling end of the shaft will be supported in the
tube and bushings from the suction spacer to the end of the shaft. To disassemble the shaft in the
vertical position, proceed as follows:
CAUTION
Failure to clamp the unit together before moving it to the
vertical position will result in damage to parts.
1. With internal assembly in a horizontal position, securely clamp internal assembly in vertical
assembly apparatus and move it to the base assembly in the work area.
2. Using two hoists and soft cables (one set attached to the vertical assembly apparatus at each
end of the internal assembly) slowly lift the free end while preventing the coupling end from
sliding and carefully tip the unit to the vertical position. Set unit on the base assembly so that
the weight of the assembly is on the suction spacer and the shaft is in suspension. Remove
cables, hoists, and vertical assembly apparatus.
NOTE
See the ASSEMBLY drawing in the back of this manual, to
determine the method used to secure the pressure reducing
sleeve (77).
4. Remove pressure reducing sleeve locknut (86 or 678) or split ring retainer (277) and split ring
(614), as applicable.
5. Heat and remove pressure reducing sleeve (77) using the procedure outlined in
INTERFERENCE FIT PART REMOVAL above. If necessary, slide the drum toward the
coupling end of shaft to clear and remove split ring (614) before removing sleeve. Remove
the pressure reducing sleeve key (88).
6. Remove the assembly rail (462).
7. At the discharge stage, proceed as follows:
a. Heat and remove the discharge impeller (34) using the procedure outlined in
INTERFERENCE FIT PART REMOVAL above. Remove the split ring (545) (if
installed) and impeller key(s) (25).
b. Heat the intermediate cover (33) adjacent to the discharge spacer (36) using the
procedure outlined in INTERFERENCE FIT PART REMOVAL above. Then remove
discharge spacer (36).
8. At the next to last stage, and each successive stage (except the first stage) proceed as follows:
a. Heat and remove the impeller (34) or spacer sleeve (24) (if installed) using the procedure
outlined in INTERFERENCE FIT PART REMOVAL above. Remove the split ring (545)
(if installed) and impeller key(s) (25).
Summary of Contents for IJ
Page 2: ...IJ PUMP INSTALLATION OPERATION MAINTENANCE ...
Page 3: ......
Page 5: ...IJ PUMP OPERATION AND MAINTENANCE MANUAL BO2660 01 iv ...
Page 11: ...IJ PUMP OPERATION AND MAINTENANCE MANUAL BO2660 01 x ...
Page 13: ...IJ PUMP OPERATION AND MAINTENANCE MANUAL BO2660 01 xii ...
Page 17: ...IJ PUMP OPERATION AND MAINTENANCE MANUAL BO2660 01 xvi ...
Page 25: ......
Page 35: ...IJ PUMP OPERATION AND MAINTENANCE MANUAL BO2660 01 2 10 Figure 2 1 Foundation Bolt ...
Page 65: ......
Page 79: ......
Page 83: ......