SVCN 7 INSTALLATION, OPERATION, & MAINTENANCE
11. Set the bar sag amount(s) determined in steps 5 through 9 above into the indicators as a plus
amount (example: an indicated -0.003 would be set in as a +0.003) while in the upright (12
o'clock) position.
NOTE
Use of a shaft alignment graph, such as Flowserve Shaft
Alignment Calculator (see Figure 2-11) aids and simplifies
the alignment process. It graphically shows the position of
the shaft centerlines in both the vertical and horizontal
planes, the shims to be added or removed, and/or horizontal
corrections to be made for accurate alignment. Further
information may be obtained through the Flowserve Service
Department.
Vertical Movement Calculations
Horizontal Movement Calculations
Movable Unit Scale
Fixed Unit Scale
+50
+40
+30
+20
+10
0
-10
-20
-30
-40
-50
-60
+60
-50
-40
-30
-20
-10
0
+10
+20
+30
+40
+50
+60
-60
180
0
90
270
3
Indicator
2
4
1
Set Bar Sag
+
÷ 2 =
2 =
÷ 2 =
4 =
180
0
90
270
3
Indicator
2
4
1
Set Bar Sag
+
÷ 2 =
2 =
÷ 2 =
4 =
50 cm
20 in.
100 cm
40 in.
150 cm
60 in.
200 cm
80 in.
0
0
SHAFT ALIGNMENT CALCULATOR
Cold
º
Hot
Pump Shop Order
Movable Unit
Fixed Unit
Measurement 1
Measurement 2
Date
Measurement 3
Location
Customer
Figure 2-11 Shaft Alignment Calculator
12. Rotate both shafts 180° (to the 6 o'clock position) and record indicator reading(s).
13. Repeat steps 11 and 12 to verify accuracy.
14. Set the bracket(s) to the horizontal (9 o'clock) position. Set indicator(s) at "0". Bar sag is not
applicable in the horizontal plane.
15. Rotate both shafts 180° (to the 3 o'clock position) and record indicator reading(s).
16. Repeat steps 14 and 15 to verify accuracy.
- 2-11 -
DO2604-13