Ensure the rubber gasket is on the inside of 

the cistern tank. Holding outlet valve in place, 

thread large plastic locknut onto threads of 

outlet valve. Hand-tighten locknut and use large 

adjustable pliers to go 1/2 turn beyond hand 

tight. 

DO NOT OVERTIGHTEN.

Once the old fitting is removed and the tank 

has been cleaned, insert the Fluidmaster outlet 

valve into position. 

Note: Position cable 

opposite to inlet fill valve and ensure 
cable does not interfere with any 
moving parts within toilet cistern.

After turning the water off, remove the old 

fitting by removing the locking nut under the 

toilet tank.

1

4

IMPORTANT: Prior to installation, turn the water off at the wall, flush toilet cistern and mop up the residual water to avoid spillage before 
removing the old outlet valve. After removing the old outlet valve, please clean the cistern tank of all dirt and grime, and ensure no debris 
is left in the tank.

Select from the following 5 applications the correct mounting method for your toilet cistern and follow the instructions

Button Part

Descriptions

FLUIDMASTER

®

 

580AU CABLE DUAL FLUSH VALVE 

INSTALLATION INSTRUCTIONS FOR TOILET CISTERN

PART# 25-1329  Grev 4  09/17

Wall Mount Cisterns:

  Connect the existing 

flush pipe to the base of the outlet valve and 

hand tighten the nut (Do not overtighten).  

Ensure the flush pipe nut washer is in good 

condition.

Button

Big Nut

REMOVE & DISCARD

REMOVE & DISCARD

REMOVE & DISCARD

Button Collar

Button Collar

Outer Flange 

Outer Flange 

Outer Flange 

Button

Outer Flange 

Button Collar

Big Nut

Small Nut

Small Nut

Small Nut

Button

Button

Button

Button Collar

Button Collar

Small Nut

Small Nut

Big Nut

Big Nut

REMOVE & DISCARD

Outer Flange 

Big Nut

Button Lock

Small Nut

Button Collar

REMOVE & DISCARD

Outer Flange 

Big Nut

Application A:

Top Push Button 38mm 

Application B:

 Top Push Button 48mm

 

Application C:

Side Push Button

Application D:

 Front Push Button 

Application E:

 16-25mm Hole 

4B. Ensure the cable runs smoothly & does not interfere with the workings of the valve.

4C. Slide button lock in; secure button box to button & release to lock.

Button Lock

  

Button Box

IMPORTANT: DO  NOT USE PLUMBER´S PUTTY TO SEAL THIS CABLE DUAL FLUSH VALVE

WM-022481

2

 

6

The over flow tube height can be adjusted up 

and down. Turn the over flow tube to the right 

to unlock. Adjust height to suit and turn the 

over flow tube to the left to lock.  Ensure top of 

overflow is 25mm below the CL (Critical Level) 

line on the inlet valve.  This is to ensure the 

correct air gap.

3

7A

A. 

To adjust 

FULL VOLUME

, first slide small  

tab to the unlock position. Push larger tab 

upwards for less water and downwards for 

more water.

B. 

To adjust 

PARTIAL VOLUME

, push tab 

inwards while sliding tab upwards for less 

water and downwards for more water.

PARTIAL

FLUSH

B

FULL

FLUSH

A

LESS

MORE

1

6

LESS

MORE

12

1

5

A

B

File Name:

25-1329_Grev4_580AU_Instructions_092817

Printing & Finishing:  4/C  Offset

Colors: 

C

M

Y

K   

DIE

PMS Colors:

Reviews: