background image

9

11

7

Forest Garden Ltd, Unit 288 Hartlebury Trading Estate, Hartlebury, Worcestershire, DY10 4JB

10

Biocidal Product Regulation (EU 528/2012) Article 58 Information

This article contains timber treated with Celcure AC-500, incorporating biocidal products to give protection against wood destroying insects & wood rotting fungi

.

Contains:

Basic copper carbonate (Copper (II) carbonate – Copper (II) hydroxide (1:1)), Boric acid, Benzalkonium chloride.

Wear gloves when handling freshly treated wood. Avoid breathing dust when cutting treated or untreated wood. Dispose of off-cuts responsibly – do not burn.

Place the barge boards against the ends of the building so that they are flush with
the overhang of the roof and in line with the top. Fix each in place using 3x40mm
screws.

Place the finial over the join making sure it is centred. Secure in place using
2x30mm screws.

Staple

Issue 0119

Maintenance.

We recommend that you treat your shed at the beginning of each season with

wood preservative treatment. Apply in

accordance with the manufacturers instructions.

Regularly check (1) All fixings are secure (2) Roofing felt is free of holes and tears (3) Sand off any rough/sharp edges.

60mm

370mm

Fix a Z’ bracket to each end of the 2275mm battens using 2 x 25mm screws for each.

Place the battens so that they bridge the door end and back end of the shed together and
position each so that the top one is offset from the apex 60mm and the second, offset 370mm
from the first as shown.

Fix the battens to the end panel’s framework using another 25mm screw to fix the Z’ bracket
down.

K

Position the staple on the door end and in line with the centre batten on the reverse of the door.
Make sure that the staple is in line with the framing behind and fix it in place using 2 x 25mm
screws.

Before fixing the Hasp to the door make sure that it is in line with the framing on the reverse of
the door and that it closes over the Staple. Fix this in place using 3 x 25mm screws.

J

I

Q

I

Place and overlap the verges at the apex. Position them equally overlapping from front to back.

Fix each Verge in place using 2 x 50mm screws and top hats at each side. Make sure that the screws locate
into the rafters and end panels.

12 x 50mm screws.

6

1.

(s)

of shed, into window opening(s),

Place the window

from the outside

so that the

bubble faces inside the shed. Lip at bottom of window must overlap board at bottom
of window opening.
2.

bottom

Place the plastic strips on the outer side and

of each window so that one

side butts up against the cladding.
3. Fix the plastic strips using 2 x security screws for each strip.
4. Place the 675mm timber strip vertically between the two window sheets so that it
overlaps both sides. Fix to the framework using 2 x security screws.

Attention:

Take care when placing

the screws. These can

not be backed out.

You may need to

cut the plastic

strips to size using

a pair of scissors

M

Inside
of Shed

Outside
of Shed

Window

Lip

Cill

Board

M

L

P

Place the sheets so that they are overlapping and are in line with the front and end panels. The
top of each sheet should be in line with the uppermost rafter you have previously fixed with the Z’
brackets.
Fix the roof sheets in place using 28 x 50mm screws and top hats

8

Reviews: