11.10
Screw on the wall plate (b).
11.11
Dismantle the fork head (e) from the valve lever (f).
11.12
Screw in the closed ball valve as far as possible, creating a seal and bringing it into
position as follows:
– The valve axis must point upwards (and not to the floor).
– The pivot motion of the valve lever must be aligned so that it is parallel to the
ceiling.
11.13
Secure the ball valve (h) with the two grub screws (g).
11.14
Mount the wall bearing linkage.
j: Rubber
k: Steel
11.15
Screw the fork head (e) to the coupling rod (l).
11.16
Mount the fork head (e) with the coupling rod to the valve lever (f).
11.17
Place the guide post (m) onto the guide (o) on the manual actuator and secure with
the grub screw (n).
11.18
Place the valve lever into the "close" position.
A: Closed
B: Open
11.19
Screw the manual actuator (q) into the fork head (p) of the deflection lever and lock
with a nut.
11.20
Using the spirit level, align the manual actuator (q) so that it is vertical.
11.21
Mark drill holes for the wall support (r) 40 mm above the triangular handle.
11.22
Drill in accordance with these markings.
11.23
Insert the wall plugs.
11.24
Screw on the guide.
11.25
Mount the wall arm in a sealing manner and bring it into position.
11.26
Screw the shower head (s) onto the wall arm (t) so that it seals.
11.27
Establish the water connection.
11.28
Check the water connection for leaks.
11.29
Plug the manual actuator if need be.
12. Function
12.1
Pull the manual actuator.
• The water will flow.
☞
The valve is not self-closing!
12.2
Place the manual actuator back in its start position.
• The water stops flowing.