background image

10

30" DUAL FUEL SLIDE-IN RANGE INSTALLATION INSTRUCTIONS

(Models with an Electric Oven and a Gas Cooktop)

Figure 12

10

 Leveling the Range - 

Level the range and set cooktop height before 
installation in the cut-out opening.

1.  Install an oven rack in the center of the oven.
2.  Place a level on the rack (Figure 12). Take 2 readings 

with the level placed diagonally in one direction 
and then the other. Level the range, if necessary, by 
adjusting the 4 leg levelers with a wrench.

3.  Taking care to not damage the countertop, slide 

range into cut-out opening and double check for 
levelness. 

9.10

 Make sure that the underside of the cooktop 

clears the countertop. If necessary, raise the unit 
by lowering the front leveling legs and the back 
leveling wheels.

9.11

 

Level the range 

(see section 10). The floor 

where the range is to be installed must be level. 
Follow the instructions under "Leveling the 
Range".

9.12

 Slide the range into the cutout opening.

IMPORTANT

 

If Accessories Needed :

9

 Range Installation

Important Note: 

Door removal is not a requirement for 

installation of the range, but is an added convenience. 
Refer to the Use and Care Guide for oven door removal 
instructions.

Standard Installation

9.1

  The range cooktop overlaps the countertop at the 

sides and the range rests on the floor. The cooktop 
is 31½" (80 cm) wide.

9.2

  Install base cabinets 30" (76.2 cm) apart. Make 

sure they are plumb and level before attaching 
cooktop. Shave raised countertop edge to clear 
31½" (80 cm) wide range top rim.

9.3

  Install cabinet doors 31" (78.7 cm) min. apart so as 

not to interfere with range door opening.

9.4

Cutout countertop exactly as shown on page 1.

9.5

Make sure the four leveling legs are setup higher 

than the height of the cabinet (shown on page 3).

9.6

 

 

Install the anti-tip bracket at 

this point before placing the range at its 
final position. 

Follow the installation instructions 

on page 13 or on the anti-tip bracket template 
supplied with the range.

9.7

  To provide an optimum installation, the top surface 

of the countertop must be level and flat (lie on the 
same plane) around the 3 sides that are adjacent 
to range cooktop. Proper adjustments to make 
the top flat should be made or gaps between the 
countertop and the range cooktop may occur. 

9.8

 

 To reduce the risk of damaging your 

appliance, do not handle or manipulate it by the 
cooktop. Manipulate with care.

9.9

Position range in front of the cabinet opening.

Installation With Backguard

The cutout depth of (21 3/4" (55.2 cm)Min., 22 1/8" 
(56.2cm) Max.) needs to be increased to 24" (61 cm) 
when installing a backguard.

Installation With End Panel

A End Panel kit can be ordered through a Service 
Center. 

Installation With Side Panels

A Side Panels kit can be ordered through a Service 
Center. Note: Install cabinet doors 31" (78.7 cm)  min. 
apart so as not to interfere with range door opening.

8

 Moving the Appliance for 

Servicing and Cleaning

Turn off the range line fuse or circuit breakers at the 
main power source, and turn off the manual gas shut-off 
valve. Make sure the range is cold. Remove the service 
drawer (warmer drawer on some models) and open the 
oven door. Lift the range at the front and slide it out 
of the cut-out opening without creating undue strain 
on the flexible gas conduit. Make sure not to pinch 
the flexible gas conduit at the back of the range when 
replacing the unit into the cut-out opening. Replace 
the drawer, close the door and switch on the electrical 
power and gas to the range.

Summary of Contents for CPDS3085KF

Page 1: ...a Refer to your serial plate for applicable agency certification 1 2 min 1 4 min WALL 5 Min 12 7 cm Min From Wall Both Sides 30 Min 76 2 cm Min 30 Min 76 2 cm Min see Note 3 18 Min 45 7 cm Min Approx 1 7 8 4 8 cm Grounded Jonction Box or Wall Outlet Should Be Located 8 to 17 20 3 cm to 43 2 cm From Right Cabinet and 2 to 4 5 1 cm to 10 2 cm From Floor Locate Cabinet Doors 1 2 5 cm Min from Cutout ...

Page 2: ...pth when it is open 21 55 25 cm D C A B Door Open Side Panel 1 1 8 2 86 cm FRONT OF CABINET FRef 22 7 8 58 1 cm min 23 1 4 59 05 cm max see Note 4 IMPORTANT To avoid cooktop breakage for cutout width E dimension of more than 30 1 16 76 4 cm make sure the appliance is centered in the counter opening while pushing into it Raise leveling legs at a higher position than the cabinet height see page 3 in...

Page 3: ...oktop Illustration 2 To successfully install the range the initial level height from floor to underside of cooktop frame should be at least 1 16 taller than cabinet sides as measured in step 2 Level the range using the four 4 leveling legs so that the height from the floor to the underside of the metal flange is greater than the tallest cabinet measurement by Metal Flange at least 1 16 see illustr...

Page 4: ...le Home Construction and Safety title 24 HUD part 280 or when such standard is not applicable the Standard for Manufactured Home Installation 1982 Manufactured Home Sites Communities and Setups ANSI Z225 1 NFPA 501A latest edition or with local codes in United States and with CAN CSA Z240 MH in Canada Make sure the wall coverings around the range can withstand the heat generated by the range Befor...

Page 5: ...is permanently grounded Disconnect power to the circuit breaker or fuse box before making the electrical connection This appliance must be connected to a grounded metallic permanent wiring system or a grounding connector should be connected to the grounding terminal or wire lead on the appliance Failure to do any of the above could result in a fire personal injury or electrical shock 1 Factory Con...

Page 6: ...ral White Wire Ground Bare Copper Wire To 240 V Receptacle A User Supplied Strain relief Must Be Installed at This Location Black Wire 1 1 8 2 9cm Dia Direct Connection Hole Punch Out Knockout for 1 3 8 3 5cm Dia Cord Kit Hole NOTE Be sure to remove the supplied grounding strap Figure 4 4 Electrical Connection to the Range U S A Three Conductor Wire Connection to Range If local codes permit connec...

Page 7: ...Connect the 2 black wires together c Connect the 2 red wires together Figure 5 3 Wire Grounded Neutral Electrical System Example Junction Box Cable from Residence Junction Box White Wire U L listed Conduit Connector or CSA listed Cable from Appliance Green or Bare Copper Wire Red Wires Neutral white Wire Black Wires NOTE Be sure to remove the supplied grounding strap Where local codes DO NOT permi...

Page 8: ...re the inlet pressure must be at least 5 12 60 cm water column 1 25 kPa Natural gas For LP Propane gas the regulator must be set for 10 25 4 cm water column 2 5 kPa manifold pressure the inlet pressure must be at least 11 27 9 cm water column 2 75 kPa The supply line should be equipped with an approved shutoff valve see Figure 10 This valve should be located in the same room as the range and shoul...

Page 9: ...ne Leak testing of the appliance shall be conducted according to the manufacturer s instructions Check for leaks After connecting the range to the gas supply check the system for leaks with a manometer If a manometer is not available turn on the gas supply and use a liquid leak detector at all joints and connections to check for leaks Do not use a flame to check for leaks from gas connections Chec...

Page 10: ...n on page 1 9 5 Make sure the four leveling legs are setup higher than the height of the cabinet shown on page 3 9 6 Install the anti tip bracket at this point before placing the range at its final position Follow the installation instructions on page 13 or on the anti tip bracket template supplied with the range 9 7 To provide an optimum installation the top surface of the countertop must be leve...

Page 11: ... for each burner Try each knob separately until all burner valves have been checked 11 4 Adjust the LOW Setting of Surface Burner Valves see Figure 13 a Push in and turn each control to LITE until burner ignites b Quickly turn knob to LOWEST POSITION c If burner goes out readjust valve as follows Reset control to OFF Remove the surface burner control knob insert a thin bladed screw driver into the...

Page 12: ...ide for phone number and address Please call or write if you have inquiries about your range product and or need to order parts Serial Plate Location 11 6 Operation of Oven Elements The oven is equipped with an electronic oven control Each of the functions has been factory checked before shipping However it is suggested that you verify the operation of the electronic oven controls once more Refer ...

Page 13: ... You may also grasp the top rear edge of the range and carefully attempt to tilt it forward to make sure range is properly anchored Figure 16 Leveling Leg Raise Lower CL 18 46 4 cm 28 1 8 71 4 cm 9 1 8 23 2 cm 12 Anti Tip Brackets Installation Instructions To reduce the risk of tipping of the range the range must be secured to the floor by properly installed anti tip brackets and screws packed wit...

Page 14: ...40 INSTRUCTIONS D INSTALLATION POUR CUISINIÈRE ENCASTRABLE DE 30 À ALIMENTATION MIXTE Modèles avec four électrique et plaque de cuisson à gaz WIRING DIAGRAM Diagrama de cables SCHÉMA DE CÂBLAGE ...

Reviews: