Installation Procedure Checklist for H-20, HS-20 with Support Columns
Note:
Please consult Installation Manual for detailed instructions.
Unloading Instructions:
Upon delivery, inspect Fuji Clean tank, both outside and inside for possible damage incurred during
transport. If you find damage, or have a question, please contact your distributor immediately.
Step 1: Prepare excavation following this instruction and drawing plan. Note: Riser height should not
exceed 24”.
Step 2: Prepare 4”- 6” bed of stone (1/8”).
Step 3: Set pre-cast concrete or pour concrete base.
Step 4: Set Adhesive anchor for binding foundation and column (4)#4 and set rebar and PVC tube or
Concrete form tube for pillar. Pour concrete to tubes.
Step 5: Use 4-point lifting lugs. Carefully lower and set tank. Level to within 1/8-inch per 2-ft.
Step 6: Re-check that tank is level to 1/8-inch per 2-ft., (fore and aft as well as side to side) and then fill
tank with fresh water to the low water line (marked inside tank). Start 24-hour water tightness test. (Please
contact your distributor or Fuji Clean USA if water level has dropped after 24 hours).
Step 7 : After concrete is hardened on support columns, backfill about ¾ way up tank in layered, compacted
6” lifts using peastone or equivalent material that form-fits into tank corrugations. Install inlet/outlet lines
using 5x4 reducing bushing if necessary.
Step 7 cont.: Using supplied adaptors and fittings, attach air pipe fitting to tank and connect to ¾” or 1”
conduit in prepared trench (min. 6” deep) to location of air blower. For CE14, 21, CEN10 and 14, locate
blower within 33’ for ¾” or 1” air line or 100’ for 1” air line. For CE30 and CEN21 use 1” air line. Connect with
no more than 5 elbows on each models.
Step 8: Locating and Installing Blower/ Control Panel.
Air Blower shall be:
in as close proximity to control panel as possible
on a solid (e.g. concrete) pad to minimize vibrations
in a location above water level
away from grease exhaust fans.
away from bedroom windows and other locations where operational sounds (although minimal)
may be a nuisance
In a location that allows unencumbered access for inspection and maintenance activity
with proper electrical grounding
with wiring and electrical connections made by a licensed electrician.
with no objects on top of electrical cord.
in a well-ventilated space out of direct sunlight and protected from elements such as direct rain
or snowfall.