This procedure details the steps required to install a standard rack. Fujitsu recommends that
the installation team familiarize themselves with the specific area where the installation is to
be performed, examine the rack, and ensure that sufficient workspace to install the rack is
available.
DAN
G
ER:
Improper handling of the equipment rack can result in serious injury or death. Always use a
forklift or lifting sling with block and tackle to lift or move the equipment rack. Keep all
personnel clear of the equipment rack while it is being lifted. Do not attempt to handle and
install the racks without sufficient assistance.
CAUTION:
The rack should be mounted on a concrete or other noncombustible surface only.
The following tools are required to perform this procedure:
■
Hammer
■
Drill
■
Drill bits sufficient to drill into the flooring
■
Punch
■
Common hand tools, including a wrench or ratchet set
Follow this procedure to install the equipment rack:
Step
Task
1
Identify the equipment rack to be installed.
2
Inspect all shipping documents to ensure that the correct shipment was received. Refer to
Section 3.4.2, Unpacking and Inspecting the Equipment Rack [p. 3-20]
3
Using the documentation supplied with the rack package, mark the floor for proper
mounting.
shows an
example
mounting diagram. Mounting diagrams will vary
depending on equipment and location.
4
Using a punch and hammer, mark the position where the holes are to be drilled.
5
Determine the type of floor anchor to be used.
Revision 1, June 2009
Summary of Contents for FLASHWAVE 7500
Page 8: ...Revision 1 June 2009 ...
Page 10: ...Revision 1 June 2009 ...
Page 16: ...Revision 1 June 2009 ...
Page 362: ...Revision 1 June 2009 ...
Page 386: ...Revision 1 June 2009 ...