CHAPTER 5
Extension Configuration
Installing the Rack
FNC-7500-0061-200
Issue 1, May 2009
FLASHWAVE 7500 Release 6.1
Equipment Installation
5-10
Fujitsu and Fujitsu Customer Use Only
12
Install the mounting bolts into the anchors, and tighten them to within 0.5 inch of the
equipment rack baseplate. Do not fully tighten at this time.
13
14
Drill the holes in the floor in accordance with the dimensions of the mounting bolts being
used.
15
Remove any debris from the area in which the rack will be mounted.
16
Move the rack into position, aligning each of the holes in the base of the rack to the anchors.
17
Install the mounting bolts with lock washers through the equipment rack baseplate and the
floor.
18
Install the nuts to the bolts under the floor. Tighten them until the lock washers begin to
compress. Do not fully tighten at this time.
19
Secure the top of the equipment rack according to the job specifications.
Some equipment racks are secured to existing overhead framework while others are secured to
an adjacent wall using a horizontal mounting brace. All overhead mounting hardware should
be tightened after assembly.
20
Tighten the floor mounting bolts.
Note:
If the rack is installed on a raised floor, there will likely be some type of supports needed.
Instructions for seismic zone installation must also be considered. Follow your local practices for
support and bracing of the rack.
21
Measure the vertical alignment of the 7-foot equipment rack. It must be vertically aligned to
within 3/16 inch.
22
Is the equipment rack within the tolerance level specified in
?
If YES:
If NO:
23
Loosen the floor mounting bolts and top mounting hardware, and adjust the equipment rack
using shims on the mounting hardware. All shims and adjustments must meet locally
acceptable guidelines.
Revision 1, June 2009
Summary of Contents for FLASHWAVE 7500
Page 8: ...Revision 1 June 2009 ...
Page 10: ...Revision 1 June 2009 ...
Page 16: ...Revision 1 June 2009 ...
Page 362: ...Revision 1 June 2009 ...
Page 386: ...Revision 1 June 2009 ...