CHAPTER 5
Extension Configuration
Installing Power, Ground, and Alarm Cables
FNC-7500-0061-200
Issue 1, May 2009
FLASHWAVE 7500 Release 6.1
Equipment Installation
5-36
Fujitsu and Fujitsu Customer Use Only
Install power, ground, and alarm cables for one rack of FLASHWAVE 7500 Extension
Configuration equipment as follows:
Identify Cabling Schematic
Step
Task
1
If you have not already done so, review the reference material presented in
2
In the following list, identify the cabling schematic appropriate for your rack configuration:
■
Rack with one Universal shelf (
■
Rack with two Universal shelves (
)
■
Rack with three Universal shelves (
Disconnect Power from CBP
3
If installing into a powered rack, disconnect office power (recommended) or remove circuit
breakers from the CBP.
4
Use a DMM to ensure 0 V DC (with reference to the battery ground) at the point of
disconnection.
Install Shelf Power Harnesses CB1
5
Refer to the cabling schematic (identified in
) to
identify the shelf that is to be connected to circuit breaker 1 (CB1).
6
Locate the rack/shelf power harness (HA15B-0001-C413,
) for the shelf.
Note:
The length of the cables may be altered at the discretion of the installer to ensure proper
length.
7
Prepare the power leads by installing the terminal lugs (wrapped in a plastic bag shipped with
the cable) that are required on one end of the cable (see
). Ensure that no
wire strands are shorting terminals together and that leads are securely fastened. The cable
should now have terminal lugs on both ends of the power cable.
Note:
The shelf power wiring is the same with all rack configurations. Observe the color coding of the
power cable.
Revision 1, June 2009
Summary of Contents for FLASHWAVE 7500
Page 8: ...Revision 1 June 2009 ...
Page 10: ...Revision 1 June 2009 ...
Page 16: ...Revision 1 June 2009 ...
Page 362: ...Revision 1 June 2009 ...
Page 386: ...Revision 1 June 2009 ...