For configurations below 32 kg:
At least two people are needed to lift the server out of
the rack cabinet.
For configurations below 55 kg:
At least three people are needed to lift the server out of
the rack cabinet.
For configurations above 55 kg:
At least four people are needed to lift the server out of
the rack cabinet.
Additionally, a lifter is required in the following cases:
–
The server weighs more than 50 kg.
–
The server weighs more than 21 kg and is to be removed above the height
of 25 U.
When using a lifter, this removal procedure needs to be carried out by
maintenance personnel.
Basic hardware procedures
RX1330 M5
Upgrade and Maintenance Manual
51
Summary of Contents for PRIMERGY RX1330 M5
Page 68: ...Basic hardware procedures 68 Upgrade and Maintenance Manual RX1330 M5 ...
Page 118: ...Power supply unit PSU 118 Upgrade and Maintenance Manual RX1330 M5 ...
Page 178: ...Fans 178 Upgrade and Maintenance Manual RX1330 M5 ...
Page 230: ...Main memory 230 Upgrade and Maintenance Manual RX1330 M5 ...
Page 256: ...Accessible drives 256 Upgrade and Maintenance Manual RX1330 M5 ...
Page 282: ...Front panel 282 Upgrade and Maintenance Manual RX1330 M5 ...
Page 290: ...Serial interface 290 Upgrade and Maintenance Manual RX1330 M5 ...
Page 336: ...System board and components 336 Upgrade and Maintenance Manual RX1330 M5 ...
Page 362: ...Appendix A 362 Upgrade and Maintenance Manual RX1330 M5 ...
Page 403: ...14 RX1330M5S SERIAL ext Cable Plan CA05973 7065 PCIe SLOT2 System Board D3929 SERIAL ...
Page 405: ...List of all used screws for PRIMERGY Servers Assembled in WCZ and FIT June 2021 ...