Hardware installation
Ê
Fit the PRIMECENTER/DataCenter rack cable management as described in
the Technical manual for the corresponding rack.
Preparing the server
Figure 9: Preparing the server
Ê
Place the inner parts of the rails on the sides of the server and secure them
with four screws.
I
Please note that the same type of rail is installed on the left and the right
side of the server. Therefore, the locking lever is released as follows:
– Left side oft the server: Push upward
– Right side of the server: Push downward
Summary of Contents for PRIMERGY RX900 S2
Page 1: ...Operating Manual English PRIMERGY RX900 S2 Server Operating Manual Edition June 2011 ...
Page 6: ...Operating Manual RX900 S2 ...
Page 10: ...Operating Manual RX900 S2 Content ...
Page 36: ...36 Operating Manual RX900 S2 Functional overview ...
Page 76: ...76 Operating Manual RX900 S2 Hardware installation ...
Page 96: ...96 Operating Manual RX900 S2 Property and data protection ...
Page 102: ...102 Operating Manual RX900 S2 Troubleshooting and tips ...
Page 110: ...110 Operating Manual RX900 S2 CSS components ...