15-1
C H A P T E R
15
Operator Panel Replacement
This chapter describes how to remove and install the operator panel. The information
is organized into the following topic:
■
Section 15.1, “Operator Panel Replacement” on page 15-1
■
Section 15.2, “Accessing the Operator Panel” on page 15-4
15.1
Operator Panel Replacement
The operator panel is a cold replacement component. This means the entire server
must be powered off and the power cords disconnected to replace the operator panel.
Note –
If you replace the XSCF unit and the operator panel simultaneously, system
will not operate normally. Execute the
showhardconf
command or the
showstatus
command to confirm that the component replaced earlier is operating normally,
before replacing the subsequent FRU.
Summary of Contents for SPARC Enterprise M4000
Page 4: ......
Page 62: ...2 38 SPARC Enterprise M4000 M5000 Servers Service Manual December 2010 ...
Page 89: ...Chapter 5 Internal Components Access 5 7 FIGURE 5 4 Removing the M5000 Server Top Cover ...
Page 126: ...6 34 SPARC Enterprise M4000 M5000 Servers Service Manual December 2010 ...
Page 132: ...7 6 SPARC Enterprise M4000 M5000 Servers Service Manual December 2010 ...
Page 158: ...8 26 SPARC Enterprise M4000 M5000 Servers Service Manual December 2010 ...
Page 245: ...Chapter 14 Backplane Unit Replacement 14 11 FIGURE 14 4 Removing the M5000 Server Backplane ...
Page 248: ...14 14 SPARC Enterprise M4000 M5000 Servers Service Manual December 2010 ...
Page 256: ...15 8 SPARC Enterprise M4000 M5000 Servers Service Manual December 2010 ...
Page 288: ...E 6 SPARC Enterprise M4000 M5000 Servers Service Manual December 2010 ...
Page 304: ...F 16 SPARC Enterprise M4000 M5000 Servers Service Manual December 2010 ...
Page 308: ...G 4 SPARC Enterprise M4000 M5000 Servers Service Manual December 2010 ...