Assembling and Installing DC Power Cables for the SPARC Enterprise T5120 Server
97
3. Connect the chassis ground wire to the facility earth ground and ensure that
this connection has proper bonding.
4. Connect the -48v or -60V return to the -48 v or -60V wires to the circuit breaker.
5. Connect the power wiring to the server by plugging each power cable into the
server power supply units.
6. When you are ready to power up the server, close the circuit breaker and
following booting procedure described in,
“Powering On the System for the First
.
Related Information
■
“Assembling and Installing the DC Input Power Cables” on page 87
Summary of Contents for SPARC Enterprise T5120
Page 1: ......
Page 2: ......
Page 6: ......
Page 22: ...xx SPARC Enterprise T5120 and T5220 Servers Installation Guide July 2009 ...
Page 64: ...42 SPARC Enterprise T5120 and T5220 Servers Installation Guide July 2009 ...
Page 88: ...66 SPARC Enterprise T5120 and T5220 Servers Installation Guide July 2009 ...
Page 120: ...98 SPARC Enterprise T5120 and T5220 Servers Installation Guide July 2009 ...
Page 128: ...106 SPARC Enterprise T5120 and T5220 Servers Installation Guide July 2009 ...
Page 132: ...110 SPARC Enterprise T5120 and T5220 Servers Installation Guide July 2009 ...
Page 133: ......
Page 134: ......