The following instructions are given for the guidance of the operator in the use of the Fulton steam
boiler. No responsibility can be accepted by Fulton Ltd if these instructions are ignored.
!
3.1
GENERAL
The following instructions are given for the guidance of the operator in the use of the J Series gas
fired steam boiler and to provide adequate information to ensure that when the boiler is put into
use it will be done safely and without risk to health. Where original equipment service manuals
are supplied, they must be read and understood in conjunction with this manual.
All warnings and cautions must be observed.
DRYING OUT TIME
The refractory casing of the boiler is made from a material that uses a high proportion of water
in the mixing process. Whilst some of the water is driven off by chemical reaction and the initial
test firing, the refractory is still ‘wet’ when the boiler is delivered. For a few days after the boiler is
commissioned and in service, water will be seen running from the bottom of the casing and from
around some branch pipes.
This is perfectly normal and part of the drying process.
SECTION 3 - OPERATION
3.2
BOILER CONTROLS
The following brief description of the controls used on the J series gas fired steam boiler is
intended to provide the operator with a basic understanding of the operating principles, which is
essential for the continued efficient operation of the boiler.
Note:
All the controls are of the ‘fail-safe’ type and are wired in series; failure of any one will automatically shut
down the boiler.
Low Water Relays and Feedwater Pump Relays.
These relays operate in conjunction with
probes suspended in the boiler and water column to automatically maintain the level of water in
the boiler and to cut off the burner should the water level fall to an unsafe level.
Steam Pressure Control(s).
Located on the control panel box and connected to the steam
pressure gauge assembly by copper tube, the pressure regulator controls the on/off cycle of the
burner, shutting the burner off when maximum pressure is reached and switching it on when the
steam pressure falls.
Note:
A set-back pressure controller is fitted when multi-boilers are fitted with a sequence control.
CONTINUED ON NEXT PAGE
Summary of Contents for J Series
Page 2: ...JGASUK IOMM 2015 2 Fulton Ltd Page II ...
Page 54: ...JGASUK IOMM 2015 2 Fulton Ltd Page 48 APPENDIX A ...
Page 58: ...JGASUK IOMM 2015 2 Fulton Ltd Page 52 APPENDIX A ...
Page 60: ...JGASUK IOMM 2015 2 Fulton Ltd Page 54 ...
Page 62: ...JGASUK IOMM 2015 2 Fulton Ltd Page 56 ...