Mounting

1. Remove the entire front cover (PSC versions) by extracting 2 screws on top front.
2. Attach uncovered power supply using 4 screw holes.
3. Make desired wire connections.
4. Reattach cover for PSC versions.

Wiring

All wiring must comply with local codes and ordinances. Disconnect power before making wiring connections to prevent 
electrical shock or equipment damage.

Hot Neut Gnd AUX

120V INPUT

24 Vac LED Indicator

Class 2, 12-18 AWG, 10 lb./in max, copper 60ºC

TRANSFORMER:

24Vac, 100VA, Class 2

Note                                                                 

Convenience Outlets & Aux. Load:

120Vac, Total Load not to exceed 9A 

*

Move internal jumper to “ALWAYS HOT” position if you wish outlets  

  to always be hot otherwise outlets will be switched by main breaker.

OUTPUT

See 

Note

COM   24 VAC

RESET

OFF

RESET

120Vac

10A Main

24Vac for Output Only

24Vac

Breaker

ON

OFF

Class 2, 12-18 AWG, 10 lb./in max, copper 60ºC

1. Bring wiring into 1 of the 2 openings on the side of the power supply while cover is removed (PSC version).
2. Make appropriate connections to the terminal strips.

Note:

 

All field wire leads are intended for installation inside the enclosure.

Voltage Check

After installation is complete, turn on power supply and perform a voltage check:
1. Place controlled equipment in operation and observe through one complete cycle.
2. Using a voltmeter, check for proper primary and secondary voltages.
3. If voltage readings are incorrect, be sure primary voltage connections are made correctly.
4. Measure voltage again:
 

a. If correct primary voltage is measured and secondary voltage is significantly less than the voltage shown on the  

 

    regulation curves, transformer winding is damaged. Replace transformer and repeat checkout procedures.

 

b. If primary voltage is 0V, be sure power supply is connected correctly or repair, if necessary. Repeat checkout

 