Malvern manual version 1.0 S.D 25.4.2014
Do not use sharp knives or instruments to open this product.
Remove the plastic film from all panels.
A.
Check with the site owner to confirm the exact installation position.
B.
Inspect the unit and panels thoroughly.
C.
Ensure all components are present inside the bath pack. (this should include : repair pot, Manual, Waste
kit, SWL sticker, lap belt, floor fixing kit and shower unit assembly. ) report any missing items immediately
quoting the number on the side of the unit.
D.
Remove any existing equipment and materials as necessary to prepare the site.
E.
Connect the bath unit on a temporary power supply . This will be indicated by a green light on the touch
pad.
F.
Raise the seat using the 2 button handset and the bath by using the touch pad.
G.
Fit the shower unit before positioning the bath in the installation position.
H.
Manoeuvre the bath into its installation position.
I.
Remove the transportation wheels and cross tie bars.
J.
Set the base distances to 1473mm
K.
Mark the position of the floor fixing holes
L.
Move the bath to allow drilling of the fixing holes
M.
Drill 4 x 10mm x 100mm deep in the floor at both ends. Clean out all dust and debris.
N.
Put in place the inner panels (wall side) and tunnel panel before fixing the bath to the floor.
O.
Re-position the bath and fix to the floor using the kit provided, ensure the plates and chrome tube are
level.
P.
Connect the hot and cold water pipes.
Q.
Connect the waste pipe.
R.
Make the electrical connection .
S.
You will need to trim the panels around the pipe work and electrical connections on the tap end of this
product.
T.
Check for any leaks and set the TMV temperatures. Taps 43°C and the Shower at 38°C
U.
Attach the safe working load to the panel and fully test the unit.
Seat end panel
assembly
Tap end panel
assembly
Fitting the lower
panels
Fitting the drive
fasteners
Securing the
panels
1473mm