Galaxy GHDXS2-1430R-16F4D Installation and Hardware Reference Manual
2-6
General Installation Procedure
5.
Cable connection:
Use the supplied power cords to connect the
subsystem to main power. It is recommended to connect power cords to
separate and independent power sources, e.g., UPS, for higher
redundancy. Make sure your subsystem is electrically grounded.
6.
Use separately purchased Fibre Channel optical cables and transceivers
to connect host ports to FC switches or host computers. (See
Chapter 3
)
CAUTION!
Cables for connecting Fibre Channel devices must be handled with care.
They must not be bent and the routing path must be carefully planned to
prevent emission interference within a rack system.
7.
Power up:
Once the components have been properly installed and all
cables are properly connected, you can power up the subsystem and
configure the RAID array. (See
Section 4.1
)
2.4.1 Installation Procedure Flowchart
Figure 2-1
shows a flowchart of the installation procedure. As you complete
each step, check off the “
Done
” box on the right. Please use this flowchart
in conjunction with the instructions that follow.
Figure 2-1: Installation Procedure Flowchart