Chapter 2: Hardware Installation
Unpacking the Subsystem
2-7
2.5 Unpacking the Subsystem
Compare the
Unpacking List
against the actual package contents to confirm
that all required materials have arrived. Carefully check the items contained
in each box before proceeding with installation.
WARNING!
Do not rely on the non-definitive, summarized unpacking list shown
below--it is for reference only. A detailed packing list can be found in your
product shipping package or product CD.
Each packed box is separated into the upper and lower levels.
Upper level box contents:
•
Sixteen (16) drive canisters
Lower level contents:
Three (3) boxes are placed in the lower level. One
(1) box contains the enclosure with all the pre-installed components. The
other two (2) boxes contain power cords and accessory items.
Accessory items include an RS-232C serial port cable, a null modem, a
printed copy of
Quick Installation Guide
, screws, and a CD containing the
RAIDWatch
Manager software and its user manual,
Installation and
Hardware Reference Manual
(this document),
MPIO
software and the
Fibre-to-SAS Operation Manual
(Firmware).
2.5.1 Preinstalled
Components
Drive trays with hard drives pre-installed.
Following are the pre-installed components:
1 - LCD keypad panel
1 - LED panel (Custom-made models)
2 - Forearm handles
2 - Chassis ears with finger grips (Custom-made models)
1 - Backplane board
2 (GHDX2-1430R-16F4D) - Controller module(s)
2 (GHDX2-1430R-16F4D) - DDR RAM DIMM module(s)
2 - BBUs (Dual-controller model, GHDX2-1430R-16F4D)
2 - PSUs (with cooling modules)
2.5.2 Components to be Installed
You must install the following components:
Hard drives (separately purchased SAS/SATA drives)
Drive trays