3.2.3 - DRILLING THE CONDENSATE DRAINAGE HOLE
•
Ensure that the hole for condensate drainage is correctly positioned. The
height should be lower than the below edge of the indoor unit.
•
Drill a 65mm diameter hole with a descending slope.
•
Seal it off with putty after installation.
Indoor side
Wall hole
Thickness of wall
Section of wall hole
Outdoor side
3.2.4 - INSTALLING THE HYDRONIC UNIT
•
Pass the piping through the hole in the wall and hook the indoor unit on
the mounting plate at the upper hooks.
•
Move the body from side to verify if it is securely fixed.
•
While pushing the unit onto the wall from the underside, hook it up on the
mounting plate at the lower part.
•
Make sure the units are firmly hooked up on the mounting plate
Hook
Putty
È severamente vietata la riproduzione anche parziale di questo manuale.
3.2.3 - CREAZIONE DEL FORO DI SCARICO DELLA CONDENSA
•
Assicurarsi che il foro di scarico della condensa sia posizionato
correttamente. L'altezza deve essere inferiore del bordo inferiore dell'unità
interna.
•
Praticare un foro di 65 mm di diametro con inclinazione discendente.
•
Sigillare con stucco dopo l'installazione.
Lato interno
Foro nella parete
Spessore della parete
Sezione del foro nella parete
Lato esterno
3.2.4 - INSTALLAZIONE DELL'UNITÀ IDRONICA
•
Passare la tubatura attraverso il foro nella parete e agganciare l'unità
interna alla piastra di montaggio sui ganci superiori.
•
Muovere il corpo da un lato per verificare che sia fissato saldamente.
•
Mentre si spinge l'unità sulla parete dalla parte inferiore, agganciarla sulla
piastra di montaggio nella parte inferiore.
•
Assicurarsi che le unità siano saldamente agganciate alla piastra di
montaggio.
Gancio