INSPECTION, HANDLING, DIMENSIONS AND
SITING
2.1 INSPECTION
On receiving the unit, check that the packing is intact: the machine left the
factory in perfect conditions and after thorough inspection.
Should you detect any signs of damage, immediately report them to the
carrier and note them on the delivery slip.
Galletti S.p.A. must be notified of the entity of the damage within 8 days of
the delivery date.
Check that the following items are present:
- putting into service report,
- wiring diagram,
- warranty certificate and list of authorised service centres,
- make sure that this manual is intact (40 pages).
2.2 HANDLING
During handling it is compulsory to check dimensions, weights, centre of
gravity and anchorages. Check as well that lifting and positioning devices
conform to the current safety regulations.
The unit leaves the factory screwed onto a wooden pallet, which allows
it to be easily conveyed with a forklift truck. After removing the unit from
the pallet, handle it gently, without applying excessive pressure on the side
panels, finned coil and fan grille.
You should collect and separate the packing materials (wood, cardboard,
nylon etc.) and make them available for recycling in order to minimise their
environmental impact.
Before lifting, remove the screws fastening the base of the unit to the wood
platform.
The unit should be lifted using Ø1½” GAS steel pipes at least 3mm thick,
to be inserted in the round holes provided on the base side members (see
figure) and identified by means of stickers. The pipes, which should protrude
by at least 250-300mm on every side, must be slung with ropes of equal
length secured to the lifting hook (provide stops at the ends of the pipes to
prevent the ropes from slipping off due to the weight).
Use ropes or belts whose length exceeds the machine height and place
spacer boards and bars on the top of the unit to avoid damaging the sides
and upper part of the unit itself.
At this point, before final positioning, it is possible to install the vibration-
damping supports (optional).
WARNING
: In all lifting operations make sure that the unit is securely anchored
in order to prevent accidental falls or overturning.