UPS for 208 Vac Grid, B60US-IB Installation Guide, doc. rel. 3.0
59
Figure 45: Reactive load testing
14.
Run the system for the desired test duration.
For example 5-10 minutes.
15.
When you have completed acceptance testing lower the active and reactive load levels
in 10% increments back down to 0 using the
Active power
slider and
Reactive power
sliders.
Transfer the system back to VF mode in order to return the UPS back to normal system
operation.
16.
Disable PQ mode (
System Menu > System > System Type > PQ Mode
).
17.
The
PQ Mode
screen appears:
Figure 46: Disable PQ mode
18.
Select
Disable
and then select
Confirm
.
Summary of Contents for B60US-IB