Gamatronic Electronic Industries Ltd.
User Guide
Page 19
µ
PS Series 3:3 Phase 10kVA (GEMS)
3.3.3
Preparation for Initial Start-Up
To prepare the UPS for initial start-up:
1.
The UPS has five main circuit breakers, at the rear of the unit.
•
INPUT CHARGER
•
ST/SW (Static-Switch)
•
OUTPUT
•
BATTERY C.B. (in horizontal position)
•
MAINTENANCE BYPASS (covered by a separate metal plate)
Verify that ALL the circuit breakers are turned OFF and that the
protective covers have not been removed (see Figure 15).
MAINTENANCE
BYPASS COVER
BATTERY C.B.
CABLE TIE
Figure 15: UPS Circuit Breakers with Protective Covers
2.
Verify that the circuit breaker in the mains electrical cabinet supplying
the UPS is OFF. No voltage should exist in the cables.